Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

MARCH 2021

TZAVELA SHAFT 

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.

MANIATIKA STATION

STATION’s OPEN CUT

The following works have been completed:

  • Completion of the permanent lining of the shaft.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Masonry walls – plastering works at levels -4, -3, -2 and -1.
  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Industrial flooring at levels -4, -3, -2, -1.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Permanent lining of the station’s main tunnel.

The following works are in progress:

  • Secondary concreting in platforms.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Masonry walls – plastering works.

The following works are in progress:

  • Surface reinstatement works.
  • Construction of perimeter wall at the expropriation boundaries.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.

The following works are in progress:

  • Pile cap beam demolition.

MELA SHAFT

The following works have been completed:

  • Concreting of the final lining of the NATM tunnel (vault + reverse arch).
  • Concreting of the foundation slab.

The following works are in progress:

  • Installation of reinforcement and concreting of the perimeter walls and the roof slab of the shaft’s pumping station.

PIRAEUS STATION 

The following works have been completed:

  • Concreting of the main station

The following works are in progress:

  • Excavation and temporary retaining of entrance 1.
  • Excavation and temporary retaining of entrance 2.
  • Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, installation of tiles at level -3, filling works at level -2, steel doors).
  • Installation of formwork, reinforcement and concreting of interior staircases.
  • High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1).

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Construction of permanent lining.

The following works are in progress:

  • Removal of scaffoldings.
  • Concrete repair works.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are put on hold:

  • Installation of doors at E/M level.

The following works are in progress:

  • Cleaning works.
  • Backfilling – compaction works at street level.
  • Installation of doors at the E/M floor.
  • Installation of floor and wall tiles in the personnel areas (ticketing level).
  • Painting works at the concourse level.
  • Installation of floor granite slabs at the platform level.
  • Painting preparatory works at staircases 7 and 8.
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, walls and platform slab.

The following works are in progress:

  • Installation of floor granites.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining.

The following works are put on hold:

  • Backfilling – compaction related works

The following works are in progress:

  • Construction of support system for wall-mounted granites in the access gallery
  • Preparation works for secondary concrete in the area where the pebbled floor is exhibited.

DIMOTIKO THEATRO VENTILATION SHAFT

The following works have been completed:

  • Concreting of the permanent lining.

The following works are in progress:

  • Pile cap beam demolition at street level.
  • Backfilling – compaction related works.
  • Painting works at the shaft.

RALLIOS SHAFT VENTILLATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.

DELIGIANNI SHAFT

 The following works have been completed:

  • Excavation and temporary retaining up to the final level
  • Waterproofing, construction of foundation slab and perimeter walls down to -3.0.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the foundation of the shaft’s permanent lining
  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

    • Concreting of the shaft’s perimeter walls (completed down
    • to -4.5)
Print Friendly, PDF & Email
WCAG