  • New Railway Station: Works for the installation of cable trays at the signaling and telecommunications technical rooms have been completed. Works for the installation of equipment of the fire fighting system in tunnels are in progress.
  • DIMOKRATIAS STATION: Works related to the installation of the air ducts network at level -1 have been completed. Works for the configuration of the surrounding area at the northern sidewalk of the station are in progress.
  • SINTRIVANI Station (Station and Crossover): The works for the concreting of the temporary openings (eastern and western) at level -3 of the Crossover have been completed.
  • PANEPISTIMIO Station: Works for the installation of signalling cables, as well as works for the installation of lifts are in progress.
  • PAPAFI Station: Works for the assembly and installation of necks of fire rated ventilation air ducts at platform level are in progress.
  • FLEMING Station: Equipment cabling related works in the technical area of the control panels of the platform screen doors are in progress.
  • ANALIPSI Station: The works for the installation of signaling equipment in the tunnels are in progress.
  • VOULGARI Station: In progress are works for the installation of fire rated air ducts at track level and for the installation of the metal structure of the platform screen doors (track 2).
  • NEA ELVETIA Station: Excavation works for the routing of PPC supply cables in the station are in progress.

DEPOT

Building Complex Ι: In progress are works for the installation of BACS cables at level +58.00 and for the installation of cable trays at level +52.00, at building 5.

Building Complex ΙΙ: Works for the installation of water pipes at level +66.40 are in progress.

TRACKWORK: The works for the construction of the floating slab/turnover 26-27 at the tunnel leading to the Depot have been completed. The works for the installation of turnover 26-27 and turnover 28-29 are in progress. Moreover, in progress are the works for the installation of the 3rd rail, the installation of cable trays, as well as alignment related works and works for the installation of signalling and telecommunications related equipment between PANEPISTIMIO Station and the Depot.