JULY 2021

TZAVELA Shaft

 The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Construction of sound absorbing plaster.
  • Traffic Arrangement – Phase B’

The following works are in progress:

  • Reinstatement works at Tzavela and Lakonias Streets.

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Completion of the permanent lining of the shaft.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Masonry walls – plastering works at levels -4, -3, -2 and -1.
  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Industrial flooring at levels -4, -3, -2, -1.
  • Installation of ceramic tiles and granites at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.12.
  • Installation of doors.
  • Installation of ventilation grids.
  • Station backfilling.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Completion of the permanent lining of the station’s main tunnel.
  • Secondary concreting in platforms.
  • Installation of granites in platforms.

The following works are in progress:

  • Installation of false ceilings and side-covering panels.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Completion of the construction of the permanent lining.

The following works are in progress:

  • Installation of granites at the entrances of the staircases and at the cross-over tunnel.
  • Installation of items supporting metal lining at the platforms, at the station’s access galleris and at the upper transverse access tunnel.
  • Installation of consolidated emergency units.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Masonry walls – plastering works.
  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Staircase secondary concreting works.

The following works are in progress:

  • Architectural finishes (painting works).

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Pile cap beam demolition.
  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.

The following works are in progress:

  • Architectural finishes (painting works).

MELA SHAFT

The following works have been completed:

  • Concreting of the final lining of the NATM tunnel (vault + reverse arch).
  • Concreting of the pumping station roof
  • Installation of reinforcement and concreting of perimeter walls.

The following works are in progress:

  • Installation of reinforcement and concreting of the shaft’s staircase.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Excavation and temporary retaining of entrances 1 & 2.
  • Construction of architectural finishes (painting works at levels -1 and -2 and installation of metal doors at levels -1, -2 and -3).
  • Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.
  • Hydro-demolition of diaphragm walls between the station and the accesses.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Painting works of the shaft.
  • Reinstatement at street level.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station

The following works are in progress:

  • Construction of routing of E/M networks at street level
  • Reinstatement at street level (flooring works using porphyry (V. Georgiou Street).
  • Installation of doors at the platform the E/M levels
  • Installation of floor granite at the ticketing level
  • Installation of floor tiles at the platform the E/M levels
  • Installation of panels at the rail-track level
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

The following works are in progress:

  • Installation of floor granite at the staircases.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

The following works are in progress:

  • Installation of wall

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining

The following works are in progress:

  • Installation of floor granite at the staircase
  • Reinstatement at street level (the concreting of the sub-base for cube stoned paving)

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY      

The following works have been completed:

  • Sealing of the temporary pumping station

The following works are in progress:

  • Painting works at the staircase

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Construction of permanent lining

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining
  • Waterproofing, construction of foundation slab and perimeter walls down to -3.0
  • Concreting of slab up to +3.00.

The following works are in progress:

  • Waterproofing of perimeter walls up to +8.5
  • Concreting of perimeter walls up to +7.5

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

  • Concreting of permanent lining of the shaft’s perimeter walls (completed up to +21.3)