Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

SEPTEMBER 2021

Πειραιάς Σεπτέμβριος 2021

TZAVELA Shaft

 The following works have been completed:

  • Permanent lining of the shaft and of the connecting tunnel.
  • Construction of sound absorbing plaster.
  • Traffic Arrangement – Phase B’.
  • Installation of doors.

The following works are in progress:

  • Reinstatement works at Tzavela and Lakonias Streets (installation of curbs, construction of gutters, sidewalk paving activities, installation of sumps, construction of rain water network, reinstatement of an old non-recorded stone duct lined with slabs).

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Permanent lining of the shaft.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Installation of ceramic tiles and granites at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.12.
  • Installation of doors.
  • Installation of false-ceilings’ supports in room 1.4.
  • Installation of steel cladding (panels) on the walls of the main areas at level -1.
  • Station backfilling.
  • Demolition of pile cap beam.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Permanent lining of the station’s main tunnel.
  • Secondary concreting in platforms.
  • Installation of granites in platforms.

The following works are in progress:

  • Installation of false ceilings and side-covering panels on the walls.
  • Installation of consolidated emergency units.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Permanent lining.

The following works are in progress:

  • Installation of steel panels at the platforms, the access tunnels of the station and at the upper transverse access gallery.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Permanent lining of the shaft and of the connecting tunnel.
  • Masonry walls – plastering works.
  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Staircase secondary concreting works.
  • Application of sound absorbing plaster.

The following works are in progress:

  • Architectural finishes (painting works).

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Permanent lining of the shaft and of the connecting tunnel.
  • Pile cap beam demolition.
  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (painting works).

The following works are in progress:

  • There are no works in progress.

MELA SHAFT

The following works have been completed:

  • Installation of reinforcement and concreting of perimeter walls.

The following works are in progress:

  • Installation of reinforcement and concreting of the shaft’s staircase.
  • Installation of reinforcement and concreting of the inner wall.
  • Installation of reinforcement and concreting of the intermediate slabs (landing).
  • Shaft waterproofing works.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Excavation and temporary retaining of entrances 1, 2 & 3.
  • Construction of architectural finishes (painting works at levels -1 and -2 and installation of metal doors at levels -1, -2 and -3, installation of granites at the east platform).
  • Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.
  • Hydro-demolition of diaphragm walls between the station and access 2 at level -2 and between accesses 1 & 3 at level -1.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Painting works of the shaft.
  • Reinstatement at street level.

DIMOTIKO THEATRO STATION

 MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station.
  • Traffic reinstatement at V. Georgiou Street.

The following works are in progress:

  • Reinstatement at street level (flooring works using porphyry – V. Georgiou Street).
  • Traffic reinstatement at V. Georgiou Street; sidewalk reinstatement on V. Georgiou Street.
  • Construction of a raised floor at room 3.4t (mechanical floor).
  • Preparation for painting works at rooms 2.4a and 2.4b at the concourse level.
  • Preparatory works for the installation of a false ceiing at the concourse level.
  • Constructionof stainless steel grooves at the staircases.
  • Installation of floor granite at the platform level.
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining.

  The following works are in progress:

  • Installation of steel panels at the platform level.

 STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

The following works are in progress:

  • Installation of wall

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of permanent lining.    

The following works are in progress:

  • Reinstatement at street level.
  • Painting works at the recess where a pebbled floor is displayed.
  • Transfer of the antiquities in the floor recess.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY   

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk reinstatement on V. Georgiou Street.

The following works are in progress:

  • Reinstatement at street level.
  • Construction of industrial flooring at the staircase.

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Construction of permanent lining.

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining.
  • Roof slab concreting (the closing of the pumping station openings are pending).

The following works are in progress:

  • Preparation works for the waterproofing of the pumping station.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining of the connecting tunnel.
  • Concreting of the shaft’s perimeter wall up to +21.3.

The following works are in progress:

  • Construction of intermediate wall (up to +3.8) and staircase down to -3.9.
Print Friendly, PDF & Email
WCAG