Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

OCTOBER 2021

Πειραιάς Οκτώβριος 2021

TZAVELA SHAFT

 The following works have been completed:

  • Permanent lining of the shaft and of the connecting tunnel.
  • Construction of sound absorbing plaster.
  • Reinstatement of Tzavela and Lakonias Streets, traffic reinstatement at Tzavela and Lakonias Streets.
  • Traffic Arrangement – Phase B’.
  • Installation of doors.

The following works are in progress:

  • Removal of temporary traffic signs (Phase B) from by-pass roads.

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Permanent lining of the shaft.

The following works are in progress:

  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.12.
  • Installation of false ceilings steel supports in the main area of the station and in the personnel areas in level -2.
  • Installation of steel cladding (panels) on the walls of the main areas at level -1.
  • Demolition of pile cap beam.
  • Construction of partition wall (street level) at the south expropriation boundaries of the station.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Permanent lining of the station’s main tunnel.
  • Secondary concreting in platforms.
  • Installation of granites in platforms.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Permanent lining.

The following works are in progress:

  • Installation of steel panels at the platforms, the access tunnels of the station and at the upper transverse access gallery.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Permanent lining of the shaft and of the connecting tunnel.
  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Application of sound absorbing plaster.
  • Installation of staircase balustrades.
  • Architectural finishes (painting works).

The following works are in progress:

  • There are no works in progress.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Permanent lining of the shaft and of the connecting tunnel.
  • Pile cap beam demolition.
  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (painting works).
  • Installation of staircase balustrades.

The following works are in progress:

  • There are no works in progress.

MELA SHAFT

The following works have been completed:

  • Concreting of perimeter walls.
  • Concreting of intermediate slabs (landings).
  • Concreting of interior wall.

The following works are in progress:

  • Installation of reinforcement and concreting of the shaft’s staircase.
  • Shaft waterproofing works.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station (works at a small section of the roof slab are pending).

The following works are in progress:

  • Excavation and temporary retaining of entrances 1, 2 & 3.
  • Construction of architectural finishes (installation of metal doors at levels -1, -2 and -3, installation of granites at the east and west platform, installation for handrails at the staircases).
  • Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.
  • Hydro-demolition of diaphragm walls between the station and access 2.
  • Hydro-demolition of diaphragm walls between the station and access 3.
  • Waterproofing of accesses 1, 2.
  • Concreting of foundation slab in access 1.
  • Concreting of exterior perimeter wall in access 2.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Painting works of the shaft.
  • Construction of staircase balustrades.
  • Polyurethane injections.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station.
  • Traffic reinstatement at V. Georgiou Street.

The following works are in progress:

  • Reinstatement at street level (flooring works at Ag. Konstantinou square and construction inner parapet walls at the square).
  • Construction of false ceiling frame at the concourse level.
  • Installation of panel supports at the platform level.
  • Installation of floor granite at the platform level and at the concourse level.
  • Construction of balustrades at staircases 7 and 8.
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining.

  The following works are in progress:

  • Installation of steel panels at the platform level.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

The following works are in progress:

  • Installation of wall

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of permanent lining.

The following works are in progress:

  • Transfer of the antiquities in the floor recess displaying the pebble floor.
  • Installation of wall granites.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY        

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk reinstatement on V. Georgiou Street.

The following works are in progress:

  • Reinstatement at street level.

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Construction of permanent lining.

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining.
  • Roof slab concreting (the closing of the pumping station openings are pending).
  • Sealing of the temporary pumping station.

The following works are in progress:

  • Sealing of the temporary pumping station.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining of the connecting tunnel.
  • Concreting of the shaft’s perimeter walls up to +21.3.

The following works are in progress:

  • Construction of intermediate wall (up to +13.4) and staircase (up to +9.4).
Print Friendly, PDF & Email
WCAG