November 2021

Καλαμαριά Νοέμβριος 2021

Kritis Shaft: Preliminary works for the industrial flooring and waterproofing of the station are in progress.
NOMARCHIA Station (Station and Crossover): Reinstatement works at the station street-level are in progress, as well as works for the installation of stainless steel balustrades in the areas where passengers will move. At the crossover preliminary reinstatement works at station street-level preliminary works for the backfilling of the ceiling slab in the area of the opening are in progress, along with and masonry works.
KALAMARIA Station: In progress are works for the reinstatement of the central isle at Pontou Street, as well as works for the installation of special aluminium items for the metal shed at the entrance of the station and works for the installation of the steel supports of its shutters. In progress are also works for the installation of the fire detection system.
ARETSOU Shaft: Reinstatement works at the station street-level are in progress, as well as works for the installation of the fire-detection system and preliminary works for the installation of the automatic fire extinction system of the station.
NEA KRINI Station: Reinstatement works at the station street-level are in progress, preliminary works for the installation of the fire-fighting system and works for the installation of the platform screen doors are in progress.
MICRA Station (Station and Crossovers): Reinstatement works at the station street-level are in progress, as well as works for the installation of stainless steel balustrades in the areas where passengers will circulate and works for the installation of electrical trays fro the power distribution, lighting and low voltage systems are in progress. In the area of the 1st and 2nd Crossover, in progress are rreinstatement works at the station street-level.
TRACKWORK: In progress are works for the installation of electrical trays and their earthing at the 1st interstation/track 1, works for the installation of cabling for the lighting system at the 1st interstation/ tracks 1 and 2, works for the installation of electrical trays at the 4th interstation/ track 2. In progress are also works for the installation of the 3rd rail throughout the entire length of the tunnel/ track 2 and the concreting of the turnout / crossover slab R100/500 in the Forestation area.