FEBRUARY 2022

TZAVELA Shaft

The following works have been completed:

  • Architectural finishes – painting works at the staircase (walls, floors).
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades.
  • Installation of the entrance hatch at street level.
  • Reinstatement of Tzavela and Lakonias Streets, opening to the

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Construction of partition walls at the station’s expropriation limits (street level).
  • Surface reinstatement (construction of sidewalk) at Etolikou and Mavromichali Streets.

The following works are in progress:

  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.14 – 3.16.
  • Installation of false ceilings and steel cladding (panels) on the walls of the main areas at the station’s level -1.
  • Installation of granites and stainless steel ducts at the staircases.
  • Construction of flower beds’ walls, slab paving works and installation of paving stones (at street level) at the station.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Steel cladding on the roof and side coverings.
  • Installation of information boards and signage at the platforms.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Installation of granites at the platforms.

The following works are in progress:

  • Installation of granites and stainless steel ducts at the staircases.
  • Installation of lining (made of steel and gypsum boards) at the access tunnels of the station and at the upper transverse access gallery.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Application of sound absorbing plaster.
  • Installation of staircase balustrades.
  • Architectural finishes (painting works).
  • Installation of access hatch at the street level.

The following works are in progress:

  • Surface reinstatement (construction of sidewalk and of surrounding area).
  • Road surface reinstatement at Koumoundourou Street.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (painting works).
  • Installation of staircase balustrades.
  • Installation of the entrance hatch at street level.

The following works are in progress:

  • Construction of perimeter wall at the eastern boundary of the expropriation.

MELA SHAFT

The following works have been completed:

  • Concreting of pit.

The following works are in progress:

  • Painting works at the staircase.
  • Installation of pit doors, installation of grid’s steel frame at street level and installation of the staircase handrails and balustrades.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station (works at a small section of the roof slab and at the stairs towards the street level are pending).

The following works are in progress:

  • Excavation and temporary retaining of entrance 3 (lift pit).
  • Construction of architectural finishes (installation of granites at level -1, construction of masonry wall and plastering works at level -1, painting works at level -2, filling works at level -1, wall cladding at the platform level, installation of false ceilings at level -3 and installation of galvanised steel panels at level -3, installation of handrails and balustrades at the staircases).
  • Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms’ level (-3).
  • High pressure water blasting at the diaphragm walls between the station and access 1.
  • Waterproofing of accesses 2 & 3.
  • Concreting of exterior and interior access walls 1, & 3.
  • Reinforcing and concreting of the roof slab at accesses 1 and 2.
  • Demolition of pile cap beam at entrance 1 and at the south front.
  • Reinforcing and concreting of the roof slab at access 2.
  • Removal of struts at access 3.

ROLOI SHAFT & NATM ACCESS TUNNEL

 The following works have been completed:

  • Sealing of the temporary pumping station.
  • Installation of emergency exit hatch at street level.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station.
  • Traffic reinstatement at V. Georgiou Street.
  • Traffic reinstatement at Karaiskou Street.

The following works are in progress:

  • Reinstatement at street level (construction of inner parapet walls at the square, backfilling – compaction).
  • Construction of false ceiling at level -1, at the concourse and the platform levels.
  • Installation of wall panels at level -1, at the concourse and the platform levels.
  • Installation of stainless steel cladding at the platforms level.
  • Installation of floor granite at the platforms level.
  • Installation of windows and glass panels at the concourse and platform levels (2.4a, 2.4b, 3.25.1, 3.25.2, 2.2, 2.3).
  • Installation of stainless steel balustrades’ stanchions at ticketing level.
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

The following works are in progress:

  • Installation of wall and ceiling panels at the staircases.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

The following works are in progress:

  • Construction of lift housing structure at street level.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of permanent lining.  

The following works are in progress:

  • Transfer of the antiquities in the floor recess displaying the pebbled floor.
  • Preliminary works for the display of the findings in a museum.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY      

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk reinstatement on V. Georgiou Street.

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Construction of permanent lining.

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining.
  • Concreting of the permanent lining.
  • Disassembly of building crane.

The following works are in progress:

  • Backfilling – compaction.
  • Pile cap beam and other concrete structures demolition at surface level.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining of the connecting tunnel.
  • Construction of the shaft’s permanent lining.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Polyurethane injections.
  • Cleaning works.