Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

ARPIL 2022

AM_Dimotiko Theatro_Progress_April 2022

TZAVELA Shaft

The following works have been completed:

  • Architectural finishes – painting works at the staircase (walls, floors).
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades and balustrades at the street-level staircase.
  • Installation of the entrance hatch at street level.
  • Reinstatement of Tzavela and Lakonias Streets, opening to the

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Construction of partition walls at the station’s expropriation limits (street level).
  • Surface reinstatement (construction of road pavement and sidewalk at Mavromichali Street).
  • Installation of glass panels at levels -1, -2.
  • Installation of lift at street level.
  • Installation of lighting poles at the sidewalk of Etolikou Street.

The following works are in progress:

  • Architectural finishes – Painting works at walls and doors at levels -4, -3, -2, -1.
  • Installation of false ceilings and steel cladding (panels) on the walls of the main areas at the station’s level -1.
  • Construction of flower beds’ walls, slab paving works and installation of paving stones and lighting (at street level).

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Steel cladding on the roof and side coverings.
  • Installation of information boards and signage at the platforms.

The following works are in progress:

  • Installation of seats in platforms.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Installation of granites and stainless ducts (gutters) at the platforms.

The following works are in progress:

  • Installation of lining (made of steel and gypsum boards) at the access tunnels of the station and at the upper transverse access gallery.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Application of sound absorbing plaster.
  • Installation of staircase balustrades – handrails.
  • Architectural finishes (painting works).
  • Installation of access hatch at the street level.
  • Road surface reinstatement at Koumoundourou Street.
  • Surface reinstatement (construction of sidewalk and of surrounding area).

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (painting works).
  • Installation of staircase balustrades – handrails.
  • Installation of the entrance hatch at street level.
  • Construction of perimeter wall at the boundary of the expropriation.

The following works are in progress:

  • Surface reinstatement (construction of sidewalk and of surrounding area).

MELA SHAFT

The following works have been completed:

  • Concreting of pit.

The following works are in progress:

  • Connection of the pumping station with the stormwater network at street level.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station (works at a small section of the roof slab and at the stairs towards the street level are pending).

The following works are in progress:

  • Construction of architectural finishes (installation of glass panes at level -1, installation of granites at level -1 , construction of masonry in access 3 at level -1, installation of doors at level -2, installation of false ceiling at level -1 and -3, painting works at levels -1 and -2 and at the staircases, wall and column cladding s at level -3, installation of galvanised steel panels at level -3, installation of handrails and balustrades at the staircases), works in the LAS, RS areas.
  • Works for the extension of the sidewalk in Akti Kallimassioti.
  • Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms’ level (-3).
  • Waterproofing of access 3 and of the lift shaft in access3.
  • Concreting of exterior and interior parapet walls, roof slab and parapet walls at street level in access 3.
  • Demolition of pile cap beam adjacent to accesses 1 and 2.
  • Removal of struts in access 3 and at the lift gallery.
  • Construction of DEDDHE pits and MV cable ducts.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Installation of emergency exit hatch at street level.

The following works are in progress:

Laying of industrial floor at the connecting tunnel and at the floor of the shaft (painting works pending).

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station.
  • Traffic reinstatement at V. Georgiou Street.
  • Traffic reinstatement at Karaiskou Street.

The following works are in progress:

  • Reinstatement at street level (construction of inner parapet walls at the square, backfilling – compaction, marble cladding works in the square).
  • Installation of wall panels at the ticketing and the mechanical floor levels.
  • Installation of false ceiling panels at the platform level and at the ticketing level.
  • Installation of stainless steel cladding at the at the platform level.
  • Installation of stainless handrails at the staircases.
  • Installation of floor granites at the platform level and at the mechanical floor.
  • Painting works in areas 2.2 and 2.3
  • Construction of fire-rated glass panes at platform level.
  • Conservation of the Project’s archaeological finds.

STAIRCASE GALLERIES

The following works are in progress:

  • Installation of supports and wall and ceiling panels.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Construction of lift housing structure at street level.

The following works are in progress:

  • Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works are in progress:

  • Transfer of the antiquities in the floor recess displaying the pebbled floor.
  • Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY     

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk reinstatement on V. Georgiou Street.

 TRIPLE TRACK NATM TUNNEL

Works have been completed.

DELIGIANNI SHAFT

The following works have been completed:

  • Disassembly of building crane.

The following works are pending:

  • Backfilling – compaction.
  • Pile cap beam and.

The following works are in progress:

  • Construction of inner parapet walls at the square.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works are in progress:

  • Painting works at the staircase and the shaft.
  • Polyurethane injections at the connecting tunnel and the shaft.
  • Installation of balustrades at the staircase.
Print Friendly, PDF & Email
WCAG