Θεσσαλονίκη Μάρτιος 2022

• New Railway Station: Completed are works for the installation of guides of the exterior roller shutters at the accesses. In progress are works for the installation of ventilation / air conditioning system equipment.
• DIMOKRATIAS Station: Completed are works for the installation of guides of the exterior roller shutters at the accesses. In progress are surface reinstatement works in the area of the south access, as well as works for the installation of cable trays at the station and the tunnels towards VENIZELOU Station.
• VENIZELOU Station: The works for the temporary detachment of antiquities along with an archaeological excavation survey continue. The archaeological excavation is also in progress at the north and at the south accesses of the station.
• AGHIA SOPHIA Station: Completed are waterproofing works at the north access, works for the installation of escalators at the south access, as well as painting works at the ticketing and mezzanine floor levels, at the accesses and at the interior lift shaft. In progress are street level reinstatement works at the north section, painting works at the exterior lift shaft, works for the installation of acoustic panels at the ventilation shaft areas, as well as cladding works with ceramic tiles in personnel areas. Moreover, in progress are preparatory works for the installation of air exhaust (OTE) and air intake (SAF) ducts at track 1 level, works for the installation of fire fighting and sewage networks, as well as works for the installation of cable trays in the technical rooms.
• SINTRIVANI Station: Completed are works for the installation of metal lining suspension sub-frames at the platform headwalls, works for the installation of window frames in personnel areas and at the ticketing level, works for the installation of guides of the metal roller shutters at the accesses, as well as works for the installation of busducts connecting the transformers with the LV general switchboard. In progress are dry construction works in ventilation areas at levels -1 and -2, works for the construction of gypsum boards in public and personnel areas, as well as works for the hydraulic connections and the installation of fan coil units (FCU) for the A/C of personnel areas.
• PANEPISTIMIO Station: Completed are works for the installation of ventilation / air conditioning air ducts at level -1. In progress are works for the construction of false ceilings using gypsum and cement boards, reinstatement works at surface level, as well as works for the installation of rail for the suspension of equipment at the west tunnel ventilation shaft.
• PAPAFI Station: Completed are works for the construction of fire stops in the technical rooms, works for the installation of metal lining suspension sub-frames at the platform headwalls, the cable connections at the outgoing branch circuit of the LV general switchboard towards the respective field equipment, the installation of data transmission infrastructure equipment in the SMR with the respective cable trays. Moreover, completed are the works for the installation of the fire detection system and the access control / intrusion detection system, works for the hydraulic connections of the pumping station, as well as works for the installation of busducts connecting the transformers with the LV general switchboard.
• EFKLIDIS Station: Completed are platform cladding works with granite slabs, as well as works for the installation of busducts connecting the transformers with the LV general switchboard. In progress are works for the installation of aluminum panels cladding above the Platform Screen Doors (PSD), works for the installation of industrial roller shutters at the accesses, works for the installation of data transmission infrastructure equipment in the SMR with the respective cable trays, as well as works for the installation of the fire detection system and the access control / intrusion detection system.
• FLEMING Station: In progress are works for the installation of the pumping station equipment.
• ANALIPSI Station: Completed is the installation of the metal structure of the exterior lift. In progress are works for the final reinstatement of Delfon Street.
• 25 MARTIOU Station: Completed are painting works at the emergency exits and at the ventilation shaft terminations, the works for the installation of trays at the ventilation shafts, the sub-frames for the installation of supports of false ceilings using gypsum boards at the accesses, as well as works for the installation of industrial roller shutters of the station. In progress are works for the installation of pumping station equipment, as well as preparatory works for the execution of individual tests concerning the station escalators.
• VOULGARI Station: Completed are works for the installation of glass panel frames in personnel areas. In progress are works for the construction of false ceiling gypsum boards at the accesses, the installation of air ducts, as well as works for the installation of the access control / intrusion detection system.

• NEA ELVETIA Station: Completed is the installation of guides of the industrial roller shutters at the accesses and the installation of the glass pane frame in the SMR area. In progress are works for the installation of sub-frames for the suspension of cladding above the PSDs, the platform lining using granite slabs, the installation of industrial roller shutters, the installation of cable trays, the installation of power distribution cables and the installation of the pumping station equipment.
DEPOT:
• Building Complex I: Completed are works for the installation of steel stripes on the false ceilings of the sanitary areas at all levels. In progress are painting works at levels +1 and +2, as well as works for the installation of the glass panel at the central entrance of the building. With regard to the electromechanical installations of Building Complex I, completed are works for the installation of equipment intended for the cooling room and the water distribution collectors and in progress are works for the installation of AI.2 AI.3 lifts.

• Building Complex II: With regard to the Administration Building and the Operation Control Centre, completed are slab cladding works at all levels, as well as tile cladding works at levels 0, +1 and +2. In progress are tile cladding works at level 3, works for the construction of frames for mineral fiber false ceilings at level +1, as well as works for the installation of the remaining exterior frames. In the Train Stabling Building, in progress are works for the installation of the remaining exterior frames. As regards electromechanical works at building 2, works for the installation of the air ducts at level +70.70.

• TRACKWORK: Completed are works for the construction of the floating slab in track 2 at Dimokratias crossover, as well as works for the installation of the turnout. In progress are works for the construction of floating slabs in tracks 1 and 2 at the interstation between NEW RAILWAY Station and DIMOKRATIAS Station. Moreover, in progress are works for the installation of the 3rd rail on track 2 between DIMOKRATIAS and VENIZELOU Stations, as well as the track-side installation of signaling equipment (track circuits and balise bases) in the tunnels from NEW RAILWAY Station to SINTRIVANI Station