Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Θεσσαλονίκη Απρίλιος 2022

• New Railway Station: In progress are works for the final surface reinstatement at street level in the area of the south access, marble cladding works at the central staircase from the ticketing level to the platform level, as well as preliminary works for the installation of Platform Screen Doors (PSD) at the side of track 1.
• DIMOKRATIAS Station: The works for the installation of PSDs are at the completion stage. In progress are works for the installation of acoustic panels at level -1 and at track level, the installation of lining and the assembly of interior escalators, as well as works for the installation of cable trays at the station and the tunnels towards VENIZELOU Station.
• VENIZELOU Station: The works for the temporary detachment of antiquities along with an archaeological excavation survey continue. The archaeological excavation is also in progress at the north and at the south accesses of the station.
• AGHIA SOPHIA Station: In progress are preparatory works for the installation of equipment bases in the technical rooms for signaling, telecommunications and UPS, as well as works for the installation of escalators at the north access.
• SINTRIVANI Station: Completed are works for the installation of the central fire detection panel. In progress are dry construction works in ventilation areas at levels -2 and -3, works for the lining of the platform headwalls using non-perforated metal panels, the installation of telecommunications equipment (cameras, loudspeakers etc.) in public areas, as well as works for the installation of air duct inlets of the ventilation / air conditioning system.
• PANEPISTIMIO Station: In progress are cabling works and works for the connection of the lighting system.
• PAPAFI Station: Completed are platform cladding works with granite slabs, works for the lining of the platform headwalls using non-perforated metal panels and works for the installation of the metal sub-frame of the benches in sanitary areas. In progress are works for the construction of false ceilings at the accesses, at the central staircase and the platform and works for the installation of telecommunications equipment (cameras, loudspeakers etc.) in public areas.
• EFKLIDIS Station: Completed are works for the installation of industrial roller shutters at the accesses. In progress are works for the installation of the sub-frame for the suspension of the non-perforated metal panels for the cladding of the platform headwalls, works for the construction of false ceilings at the platform, as well as preparatory works for the construction of a sample of the shed at entrance 1.
• FLEMING Station: Completed are works for the hydraulic connections of the pumping station and the installation of the bus-ducts connecting the transformers and the LV general switchboard at the lighting and power supply substation. In progress are platform cladding works with granite slabs, works for the installation of a frame for the suspension of the false ceiling using cement boards at the central access, works for the installation of the sub-frame for the suspension of aluminum panels, as well as works for the installation of the fire detection system and the access control / intrusion detection system.
• ANALIPSI Station: Completed is the implementation of the final traffic arrangement of Delfon Street with 2+2 traffic lanes. In progress are surface reinstatement works, platform cladding works using granite slabs, as well as works for the connection of the BACS equipment.
• 25 MARTIOU Station: Completed are works for the installation of elevated floors in the areas of the Station Master Room (SMR) and the ticket office. In progress are works for the installation of air ducts and the equipment for tunnel ventilation and ventilation / air conditioning, hydraulic connections of the pumping station, the installation of the fire detection system, as well as works for the connection of the BACS equipment.
• VOULGARI Station: Completed are works for the installation of the sub-frame for the suspension of the non-perforated metal panels for the cladding of the platform headwalls. In progress are connection related works of the BACS equipment, works for the installation of the fire detection system, as well as equipment earthing works.

• NEA ELVETIA Station: Completed is the construction of elevated floors of the PSD equipment technical rooms, of the UPS systems as well as of the SMR. In progress are marble cladding works at access 2 and works for the installation of an elevated floor at the LAS.
DEPOT:
Building Complex I: Completed are works for the installation of frames for mineral fiber false ceilings in office areas and corridors at all levels, works for the installation of the glass panel at the central entrance and works for the installation of benches and wash basins in all sanitary areas. In progress are works for the installation of glass panels and of the interior glass panel of the canteen, as well as flooring works in parking areas at level -2. With regard to the electromechanical installations, completed are works for the installation of A1.3 lift, while in progress are works for the installation of A1.2 lift, the connection of the fire detection system equipment, the installation of chimneys, as well as tests of the compressed air supply network.

Building Complex II: With regard to the Administration Building and the Operation Control Centre, in progress are marble cladding works of staircase K2.8, as well as waterproofing works at the planted terraces. In the Train Stabling Building, in progress are marble cladding works of the staircases of building V, as well as works for the installation of special items at the roof of building V. As regards electromechanical works, in progress are works for the construction of cooling room collectors, the installation of the water distribution collector, as well as cabling works for the weak current equipment in the washing plant. In the surrounding area, in progress are works for the reinstatement of Er. Stavrou street.

TRACKWORK: Completed are works for the construction of the floating slab at track 1 at the interstation between NEW RAILWAY Station and DIMOKRATIAS Station. The construction of the floating slab in track 2 up to the aforementioned interstations is at the completion stage. Moreover, in progress are works for the disassembly of the temporary line and for the installation of the rubber sub-base of the floating slab at the crossover of the NEW RAILWAY Station. In addition, in progress are works for the installation of the 3rd rail between DIMOKRATIAS and AGHIA SOFIA Stations.

Print Friendly, PDF & Email
WCAG