April 2022

iso

• NOMARCHIA Station (Station & Crossover): In progress are works for the installation of a lift housing structure at street level. In the area of the Crossover in progress are works for the completion of the installation of cylinders of the automatic gas fire suppression system.
• ARETSOU Station: In progress are works for the installation of transformer bases in the lighting/ auxiliary power and the traction power substations.
• MICRA Station: In progress are preliminary works for the installation of the Platform Screen Doors system.
• TRACKWORK: In progress are works for the construction of crossovers/ crossing in the area of Nomarchia Crossover, as well as works for the installation of handrails inside the tunnel, track 1.