Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Θεσσαλονίκη Ιούνιος 2022

New Railway Station: Completed are marble cladding works at the central staircase, from the ticketing level to the platform. In progress are marble cladding works at the fixed staircase of the north access, works for the installation of Platform Screen Doors (PSD) as well as works for the installation of guides for aluminum panel lining and marble cladding at the ticketing level.
DIMOKRATIAS Station: Completed are surface reinstatement works at the junction of 26 Octovriou street and Monastiriou street. In progress are the respective works at the junctions of Dodekanissou/Polytechniou streets and 26 Octovriou/Polytechniou streets. Moreover, completed are the works for the construction of false ceiling made of gypsum boards in the area of the northern access and works for the installation of guides for aluminum panel lining at the ticketing level. In progress are marble cladding works at the ticketing level, as well as cable installation works.
VENIZELOU Station: The works for the temporary detachment of antiquities along with an archaeological excavation survey continue. The archaeological excavation is also in progress at the north and at the south accesses of the station. At the east part of the station (level -1), completed are the works for the installation of struts, while the first phase of excavation of this section towards level -2 is at the completion stage. Moreover, in progress are the preliminary works for the installation of struts at the west part of the station.
AGHIA SOPHIA Station: Completed are works for the installation of air exhaust/ intake ducts at the track level, the installation of escalators and of the perimeter angle to support the elevated floors in the technical rooms. In progress are works for the installation of doors in the technical rooms, as well as works for the installation of air ducts of the ventilation-A/C network.
SINTRIVANI Station: Completed are dry construction works in ventilation areas at levels -2 and -3, as well as works for the installation of air duct inlets of the ventilation- A/C system, the aluminum panel lining at the central staircase as well as the installation of the false ceiling made of gypsum board. In progress are works for the completion of the marble cladding in the public areas, the installation of removable handrails, the final painting works in the technical rooms, as well as the works for the installation and connection of the lighting switchboards in the LAS substation area.
PANEPISTIMIO Station: Completed are works for the installation of handrails at the emergency exits, works for the lining of the platform headwalls using non-perforated panels, works for the installation of elevated floors in the technical rooms for the automatic PSD equipment, UPS related works, works at the station master room and at ticket office, works related to the hydraulic connections of the heat pump of the A/C system, the construction of the discharge network of the pumping station, as well as the installation of the foundation bases of the lighting switchboards. In progress is screed paving works at the staircase of emergency exit K10, reinstatement works at the central traffic island of Egnatias street, in the surrounding area of the Aristotle University of Thessaloniki and in the area of the University Campus, as well as the works for the installation of fire detection and automatic fire extinguishing using gas, at the LAS.
PAPAFI Station: Completed are works for the installation of elevated floors in the technical equipment rooms for PSDs and UPS, while the new guard house of Papafio Institution has been delivered. Moreover, completed are works for the installation of telecommunications equipment in the public areas (loudspeakers, PIS etc.), the construction of the discharge network of the pumping station, works for the installation of foundation bases of the lighting switchboards in the LAS, as well as works for the installation of the fire detection alarm panel in the fire extinguishing area. In progress are works for the installation of a gypsum board made of non perforated metal sheets on the platform, the installation of the elevated floor in LAS, the installation of vertical lining made of non perforated metal sheets at the station levels, as well as works for the installation of the automatic extinguishing system using gas in the technical room.
EFKLIDIS Station: Completed are works for the installation of non perforated metal panels for the cladding of the platform headwalls, the installation of the elevated floor at the station master room and in the technical rooms of the PSD and UPS equipment, the installation of the telecommunications equipment in the public areas, the construction of the discharge network of the pumping station and the installation of the foundation bases of the lighting switchboards in the LAS area. In progress are works for the construction of fire stops, the construction of the shed of entrance 1, as well as works for the installation and the connections of the lighting switchboards.
FLEMING Station: Completed is the installation of the foundation bases of the lighting switchboards in the LAS. In progress are marble cladding works in the public areas, works for the installation of elevated floors in the technical equipment rooms for PSDs, UPS, the station master room and the ticket office, as well as preparatory works for the installation and connections of the tunnel ventilation switchboards and the air exhaust/ intake fans.
ANALIPSI Station: As regards the surface reinstatement works, completed is the construction of sidewalks at Delfon street, while in progress are works for the construction of the storm water network at Drossini street, as well as works for the relocation of networks from the area of the 8th High School at Delfon street. Moreover, completed are flooring works using granite slabs at the east access, as well as works for the installation of the frame for the suspension of false ceilings in public areas. In progress are marble cladding works in the public areas and at the fixed staircase towards the platform.
25 MARTIOU Station: Completed are vertical marble cladding works at the east access, works for the installation of suspension frames for false ceilings in the public areas, as well as works for the installation of lining of the platform headwalls. In progress are surface reinstatement works, marble cladding works at the central staircase, as well as works for the construction of equipment earthing.
VOULGARI Station: Completed are flooring works at the platform using granite slabs and in progress are works for the installation of wall lining using aluminum panels.
NEA ELVETIA Station: In progress are marble cladding works at entrance 3, works for the installation of false ceilings suspension at the platform, works for the construction of fire stops in the technical rooms, works for the completion of granite flooring at the ticket issuing level, as well as works for the construction of earthing.

DEPOT:
Building Complex I: In progress are industrial floor painting works, works for the installation of parapet covers, the installation of wooden doors and striping works. As regards the electromechanical installations, in progress are works for the connection of AC units, as well as works for the installation of lighting switchboards in the complex.

Building Complex II: In progress are works for the installation of frames for the suspension of ceilings made of mineral fibers, staircase lining works using marble and painting works. As regards the electromechanical works, in progress are works for the installation of air ducts and A/C piping, the installation of piping at the heating plant and the central A/C unit, works for the installation of air ducts as well as cable installation works. In the surrounding area, in progress are works for the installation of lighting poles, as well as works for the construction of curbs, sidewalks, gutters and roadworks at the interior streets.

TRACKWORK: Completed are works for the construction of the crossover at the NEW RAILWAY Station, while in progress is the construction of turnouts at the Forestation. In addition, in progress are works for the installation of the 3rd rail between DIMOKRATIAS and the NEW RAILWAY Stations, as well as the installation of the trackside signaling equipment in the tunnels from NEW RAILWAY Station up to SINTRIVANI Station.

Print Friendly, PDF & Email
WCAG