Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Καλαμαριά Ιούνιος 2022

NOMARCHIA Station: In progress are works for the installation of metal bases for the foundation of transformers at the LAS substation.
KALAMARIA Station: In progress are works for the installation of monorail.
ARETSOU Station: In progress are works for the installation of a network and equipment for the ventilation-A/C system, as well as works for the installation of a network for automatic fire extinguishing using gas.
TRACKWORK: Completed are works for the installation of 3rd rail in Nomarchia Crossover area, while in progress are works for the installation of handrails in the tunnel, track 1, and works for the installation of fire fighting network at interstation 1.

Print Friendly, PDF & Email
WCAG