Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

AUGUST 2022

TZAVELA Shaft

The following works have been completed:

  • Architectural finishes – Painting works at the staircase (walls, floors).
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades and balustrades at the street level staircase.
  • Installation of the entrance hatch at street level.
  • Installation of roller shutters.
  • Reinstatement of Tzavela and Lakonias Streets, opening to the

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street).
  • Installation of glass panels at levels -1, -2.
  • Door painting works.
  • Installation of lifts at street level and at level -2.
  • Installation of lighting poles at the sidewalk of Etolikou Street.
  • Reinstatement of road pavement in Mavromichali Street at the west of the station.

 The following works are in progress:

  • Architectural finishes – Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.
  • Installation of steel cladding (panels) on the walls/ceilings and of metal side covers at the station’s escalators.
  • Installation of stainless steel handrails.
  • Installation of the station’s signage.
  • Construction of partition walls at the station’s south expropriation limits (street level)
  • Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street)
  • Slab paving works and installation of paving stones and lighting at street level.
  • Laying of planting soil at the station’s flower beds.
  • Connection of the station with EYDAP network.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Steel cladding on the roof and side covers.
  • Installation of information boards and signage at the platforms.
  • Installation of seats at the platforms.
  • Installation of radio communication (TETRA) cable.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Installation of granites and stainless ducts (gutters).
  • Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
  • Installation of lifts glass panes.
  • Installation of metal side covers and handrails at the station’s escalators.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades – handrails.
  • Architectural finishes (re-painting works).
  • Door painting works.
  • Installation of access hatch at the street level.
  • Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (re-painting works).
  • Door painting works.
  • Installation of staircase balustrades – handrails.
  • Installation of the entrance hatch at street level.
  • Construction of perimeter parapet walls at the boundary of the expropriation.
  • Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.

MELA SHAFT

The following works have been completed:

  • Concreting of pit.

 PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Construction of architectural finishes (filling works, installation of granites at levels -1 and -3, installation of false ceiling at levels -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, installation of glass panes at level -1, wall and column cladding works at level -3 and side coverings at the public staircases, painting of doors and installation of their accessories, works in the LAS, RS areas.
  • Electromechanical works at levels -1 and -2.
  • Installation of granites and marbles at street level.
  • Installation of gutters, curbs and construction of sidewalks inside and outside the main worksite area and installation of ILPAP columns.
  • Installation of shaft grids.
  • Works for the construction of the asphalt sub-base to bring back the street above station level.
  • Network reinstatement works at street level (PPC, OTE, sewage, etc.)
  • Asphalt paving at the street section in front of the Suburban Railway Station.
  • Works for the installation of station lifts (frame – glass panes).
  • Installation of plant irrigation network and other reinstatement works at street level.
  • Installation of signs at the platform and ticket issuing levels.

ROLOI SHAFT & NATM ACCESS TUNNEL

 The following works have been completed:

  • Sealing of the temporary pumping station.
  • Installation of emergency exit hatch at street level.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Opening of V. Georgiou and Karaiskou Streets to the traffic.

The following works are in progress:

  • Reinstatement at street level.
  • Painting of the floor of the mechanical level.
  • Installation of false ceiling at the ticketing level and at the platform level.
  • Installation of floor granites at the ticketing level and at the platform level.
  • Installation of glass panes at the lift pits.
  • Construction of stainless cladding, stanchion and balustrades at the ticketing and at platform levels.
  • Installation of ironmongery on the doors.
  • Assembly-disassembly of building crane.
  • Conservation of the Project’s archaeological finds.

STAIRCASE GALLERIES

The following works are in progress:

  • Installation of supports and wall and ceiling panels.
  • Installation of handrails at the staircases.
  • Installation of floor granites.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Construction of lift housing structure at street level.

The following works are in progress:

  • Reinstatement at street level.
  • Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
  • Implementation of the design for the display of the archaeological finds in the recess.
  • Wall-mounted granites at the staircase termination point at street level.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works are in progress:

  • Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
  • Installation of granite floors.
  • Implementation of the design for the display of the archaeological finds in the recess.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY   

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk traffic reinstatement on V. Georgiou Street.

 The following works are in progress:

  • Reinstatement at street level.

 TRIPLE TRACK NATM TUNNEL

Works have been completed.

DELIGIANNI SHAFT

The following works have been completed:

  • Disassembly of building crane.

The following works are in progress:

  • Construction of parapet walls at the square.
  • Demolition of pile cap beam.
  • Backfilling-compaction works.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works are in progress:

  • Reinstatement at street level.
  • Construction of shaft safety railing.
Print Friendly, PDF & Email
WCAG