Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Θεσσαλονίκη Ιούλιος 2022
  • New Railway Station: Completed are works for the installation of Platform Screen Doors (PSD). In progress are works for the installation of cable trays at levels -1 and -2 and at the tunnel leading to DIMOKRATIAS Station.
  • DIMOKRATIAS Station: Completed are surface reinstatement works at the junction of Dodekanissou and Polytechniou Streets. The respective works at the junction of 26 Octovriou and Polytechniou Sreets are at a completion stage. Completed are also works for the installation of sub-frames above the platform screen doors in track 2. In progress are works for the installation of sound-absorbing lining at the ventilation shafts, works for the installation of cable trays at the station and at the tunnel with direction to VENIZELOS Station and cable installation works.
  • VENIZELOU Station: The works for the temporary detachment of antiquities along with the rest of the archaeological excavation survey at the central section have been completed. The archaeological excavation is in progress at the north and at the south accesses of the station. At the east part of the station, completed are the works for the excavation of this section up to level -2. In progress are works for the installation of reinforcement for the construction of the reinforced concrete slab. At the west section of the station, completed are woks for the demolition of the central piles and works for the installation of struts, while in progress is the excavation of the section in question towards level -2. Moreover, in progress are excavation works for the station’s south-east ventilation shaft and the archaeological monitoring which is being concurrently carried out.
  • AGHIA SOPHIA Station: Works for the construction of the permanent retaining of the archaeological area in the north access. In progress are street-level reinstatement works and works for the final display of antiquities in the area of the south access. In progress are also works for the installation of doors in the technical rooms and in the personnel areas.
  • SINTRIVANI Station: Completed are works for the installation of the vertical marble cladding in the public areas, the installation of telecommunication equipment in public areas (loudspeakers, passenger information system, etc.) and the installation of glass panes in personnel rooms.
  • PANEPISTIMIO Station: Completed are works for the construction of the central traffic island of Egnatias Street, screed laying works at the emergency exit K10 staircase and works for the installation of fire detection and automatic fire extinguishing using gas at the LAS. In progress are reinstatement works in the surrounding area of Aristotle University of Thessaloniki and in the area of the University Club.
  • PAPAFI Station: Completed are works for the installation of the automatic fire extinguishing using gas in a technical room and works for the installation of removable balustrades in the ventilation shafts. In progress are works for the cladding of the piers of the fencing of Papafi Institute and works for the completion of the vertical marble cladding works.
  • EFKLIDIS Station: Completed are works for the construction of the earthing in LAS, while in progress are works for the construction of suspended ceiling at platform level and works for the construction of fire stops and works for the construction of the shed of entrance 1.
  • FLEMING Station: In progress are roadworks, grading works, works for the installation and connections of the tunnel ventilation mimic panels and the air exhaust/ intake fans.
  • ANALIPSI Station: In progress are works for the construction of sidewalks, works for the construction of the storm water network at Drossini Street, as well as works for the relocation of networks from the area of the 8th High School at Delfon Street. Moreover, in progress are works for the installation of air ducts for the ventilation/air conditioning and tunnel ventilation and works for the installation of cables.
  • ΝΕΑ ΕLVETIA Station: Completed are the platform lining works using granite slabs, while in progress are works for the installation of door/window frames and glass panes in personnel areas, works for the installation of distribution cables, the construction of earthing, as well as works for the installation of the ventilation/A/C system.
    DEPOT
    Building Complex Ι: In progress are works for the installation of furniture and partitions separating offices, painting works, works for the construction of false ceilings, the construction of fire stops, as well as the installation of iron-mongeny items, doors and grillages for shafts. As regards the electromechanical installations, completed is the installation of lighting and fire detection systems, the installation of lighting switchboards as well as the installation of chimneys. In progress are works for the construction of A/C piping insulations, the connection of A/C units, the installation of sanitary appliances and taps, works for the installation of mimic panels of the ventilation/A/C system and the pumping rooms, works for the installation and connections of the BACS system panels, the installation of sprinklers, as well as works for the installation of the fire detection system.
    Building Complex ΙΙ: In progress are works for the installation of linoleum, glass panes, balustrades, works for the construction of false ceilings, as well as works for the installation of fire rated door/window frames. As regards the electromechanical works, in progress are works for the installation of piping of the heating plant and the central A/C unit, works for the insulation of A/C pipes, works for the installation of fire detection, access control and intrusion detection systems, works for the installation of network cables and works for the installation of lighting fixtures. In the surrounding area, in progress are works for the installation of lighting poles, the installation of the pedestrian bridge deck, as well as roadworks at the interior streets.
    TRACKWORK: Completed are works for the construction of turnouts 3,4,5 while at the completion stage are works for the construction of turnouts 1,2 at the Forestation. In addition, in progress are embedding works of the prefabricated cable ducts between DIMOKRATIAS and the NEW RAILWAY stations, as well as works for the installation of the trackside signaling equipment in the tunnels from NEW RAILWAY Station up to SINTRIVANI Station.
Print Friendly, PDF & Email
WCAG