Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Θεσσαλονίκη Ιανουάριος 2023
  • New Railway Station: Completed are works for the installation of the vertical marble cladding at the accesses and the installation of granite slabs on the platform floor. In progress are works for door painting at the technical rooms, installation of grilles at the tunnel ventilation shafts, the construction of gypsum boards and fiber boards, the installation of stainless steel stanchion poles, the works for the installation of lighting cables in the tunnels, works for the connection of the signaling equipment and works for the installation of the pumping station discharge pipes network.
  • DIMOKRATIAS Station: Completed are works for the installation of traction power and cables. In progress are works for the construction of marble cladding at the inner staircases, works for the construction of fire dampers, works for the installation of electric conduits at level -1, works for the installation of cables intended for low voltage systems at all levels, as well as works for the installation of the lighting system in tunnels.
  • VENIZELOU Station: Completed are works for the construction of parapet walls and of the platform slab, the construction of perimeter walls made of reinforced concrete at all levels of the station, as well as the dismantling of the temporary retaining piles in the area of the southern access of the station. In progress are the works for the construction of masonry walls at the platform and the electromechanical facilities levels, works for the installation of struts at the southern access, as well as the works for the installation of scaffoldings for the construction of the foundation slab intended for the archaeological finds at the eastern part. Moreover, in progress is the construction of trackwork in the station area, and more precisely: the installation of cables embedded conduits, the laying of the invert concrete and the installation of the weak current trays. In progress is the archaeological survey at the two (northern and southern) accesses of the station.
  • AGHIA SOPHIA Station: Completed are the works for the installation of tracks intended for equipment suspension in the ventilation shafts of the tunnels, the works for the reinstatement of the sidewalks at street level, except for a section of the southern access area, as well as the works for the installation of the gypsum board above the platform doors at track 2. In progress are the works for the installation of acoustic panels, the works for the installation of the air-ducts network and the ventilation/air-conditioning equipment at the mezzanine level, as well as the works for the installation cable trays in the tunnels.
  • SINTRIVANI Station: Completed is the installation of false ceilings using perforated panels, the installation of guidance tiles for PSNs, the works for the installation of the mimic panels of the tunnel ventilation system and the stations ventilation/air conditioning system, as well as the installation of hatches at platform level. In progress are the works for the installation of stainless steel handrails and balustrades.
  • PANEPISTIMIO Station: Completed are the aluminum panels’ lining works at level -1, the construction of the false ceiling at the platform and the installation of emergency consolidated units. In progress is the construction of false ceilings in public areas, the installation of guidance tiles for PSNs, the installation of stainless steel handrails, as well as the works for the installation and connection of the lighting boards.
  • PAPAFI Station: Completed are the works for the installation of the food and beverage equipment in the personnel’s rest room, the works for the installation of ironmongery at the doors, the installation of stainless steel handrails and balustrades, the installation of pits in the surrounding area, the installation of guidance tiles for PSNs, and the installation of hatches at platform level. In progress are the works for the fencing of Papafio Foundation, the works for the construction of sheds at street level, as well as the testing of the electromechanical systems.
  • EFKLIDIS Station: Completed are the final painting works, the works for the construction of false ceilings, the works for the construction of the two – out of the three – sheds of the station, the installation of pits in the surrounding area,  the installation of stainless steel handrails and balustrades, the installation of guidance tiles for PSNs, as well as the installation of the food and beverage equipment in the personnel’s rest room. In progress are the works for the construction of the last shed at surface level.
  • FLEMING Station: Completed are the works for the installation of guidance tiles for PSN, the installation of stainless steel handrails and balustrades, the installation of the mimic panel of the ventilation/air conditioning system and connection related works, as well as the construction of false ceilings, while in progress are final painting works, works for the installation of vertical lining using aluminum panels, works for the construction of cladding using steel panels, works for the completion of the installation of the fire-detection and of the access control / intrusion detection systems, works for the connection of lighting cables and telecommunication systems, as well as for the installation of the respective equipment, as well as works for the completion of the installation of the ventilation/air conditioning systems.
  • ANALIPSI Station: Completed are granite cladding works at the eastern and western access, works for the installation of the false ceiling at the platform, the installation of mimic panels of the tunnel ventilation system, the installation of frames of the advertising panels at track level, as well as works for the installation of equipment in the station master room. In progress are works for the completion of false ceilings in public areas and vertical marble cladding works at the fixed staircase, works for the installation of guidance tiles for PSNs, as well as works for the completion of facilities at the Lighting and Auxiliary Power Supply (LAS).
  • 25 MARTIOU STATION: Completed are works for the installation of lighting switchboards, works for the installation of the mimic panel of the ventilation/air conditioning system and connection related works, works for the installation of air ducts and equipment of the ventilation/air conditioning system, the installation of a Fan Coil Unit (FCU) in the station master’s room, as well as works for the installation of the consolidated emergency units at the platform. In progress are works for the installation of the Access Control System/Intrusion Detection System, as well as final painting works of technical rooms and doors.
  • VOULGARI Station: Completed is the installation of the automatic fire extinguishing system/gas in the technical rooms. In progress are works for the installation of the mimic panel of the ventilation/air conditioning system and connection related works, the installation of the outdoor lift of the station, the installation of the sound-absorbers of the tunnel ventilation system, works for the completion of the galvanized balustrades at the emergency staircases, as well as works for the installation of stainless steel stanchions for balustrades.
  • NEA ELVETIA Station: Completed are works for the installation of the mimic panels of the tunnel ventilation system, as well as works for the installation of FCUs. In progress are works for the connection of tunnel ventilation mimic panels, the installation of lighting cables, the installation and connections of the mimic panel of the ventilation/air conditioning system, the installation of sound absorbers of the tunnel ventilation system, the construction of fire dampers, final painting works of technical rooms and doors, as well as cladding works using aluminum panels in the public areas.

DEPOT

  • Building Complex Ι: Completed are fire rated painting works at the indoor levels. In progress are works for the installation of exterior aluminum louvers and works for the installation of covers for seismic joints. With regard to electromechanical installations, in progress are works for the installation of the water supply pipe network, the supply of compressed air and sockets, the construction of an air duct network and the installation of the fire detection system, as well as chimney installation related works.
  • Building Complex ΙΙ: With regard to the Administration Building and the Control Centre, completed are lining works using ceramic tiles at all levels. In progress are works for the installation of wooden doors and ironmongery, works for the installation of mineral fiber false ceiling in the office rooms, floor cladding works using linoleum, works for the installation of the remaining exterior frames and the interior aluminum glass panels, as well as works for the installation of stainless steel lining on the walls of the lifts at all levels. In Building 2, completed are works for the installation of exterior lining using panels, while in progress are works for the construction of wooden floors at the lofts, as well as works for the installation of glass panels and the interior aluminum glass panels. With regard to the electromechanical works at Building Complex 2, in progress are works for the installation of air conditioning networks, the installation of the lighting system, fiber optics, the installation of water supply pipes at building 3, sewage pipes at building 4, works for the installation of natural gas piping and fire-fighting pipes, works for the installation of cable trays, power distribution, lighting and fire detection at building 9, as well as works for the construction of lifts. In the surrounding area, completed are works for the installation of natural gas pipes network, as well as the works for the construction of networks and manholes related to electromechanical systems. In progress are works for the construction of the water supply pipe network and the installation of fire-fighting valves, works for the construction of curbs, sidewalks and gutters at the inner street, as well as works for the arrangement of the Public Utility Organizations networks and the construction of curbs, sidewalks and gutters in the framework of the reinstatement of Possidonos Street.
  • TRACKWORK: Preparation for the commencement of installation of trackwork at VENIZELOU Station.

In progress are testing and commissioning works.

Print Friendly, PDF & Email
WCAG