October 2015

  • AGHIA VARVARA Station: The works for the removal of precast segments of the false tunnel are in progress;
  • MANIATIKA Station: In progress are the excavation and temporary retaining works of phase A1 (south front – eastern gallery and north front – western gallery) of the station’s main tunnel.
    In progress are the phase A2 excavation and temporary retaining works (south front – eastern gallery – south front – western gallery);
  • PIRAEUS Station – Roloi shaft: the archaeological excavation is in progress;
  • DIMOTIKO THEATRO Station – Ventilation Shaft: The archaeological excavation and dismantling works were completed. At the triple track NATM tunnel towards the University of Piraeus, in progress are the Phase A excavation works (27m/140m already excavated), as well as the Phase B excavation works (27m/63m already excavated). At Panepistimio shaft, in progress is the archaeological investigation in the PUO network diversion areas. The works for the maintenance of TBM and the partial relocation of the TBM worksite are in progress. The tunnel excavation has been completed by 50.34%.