September 2015

  • AGHIA VARVARA Station: The works for the construction of perimeter walls and columns up to the mechanical floor level, as well as the works for the construction of the mechanical floor slab are in progress;
  • NIKEA Station: The construction of a part of the roof slab of the main Station, as well as the TBM maintenance works are in progress;
  • MANIATIKA Station: In progress are the works for the construction of rock anchors of the Station main building;
  • PIRAEUS Station: At Roloi shaft, in progress is the archaeological excavation;
  • DIMOTIKO THEATRO Station: At the main Station, at Aghiou Konstantinou square, waterproofing & concreting works of the foundation slab and the perimeter walls have been completed up to the platform level;
  • Tunnel boring works have been completed by 50%.