April 2014

  • The works for the construction of cap beam, excavation and temporary retaining, temporary drainage of the raft and the construction of the foundation slab are completed, while waterproofing works and works for the construction of walls are in progress at AGHIA VARVARA Station;
  • The worksite fencing, as well as the archaeological investigation trenches at Taxiarchon Shaft of AGHIA VARVARA Station, were completed;
  • The works for the construction of piles and the cap beam at KORYDALLOS Station were completed, while the general excavation at the final level is at the final level (level 7);
  • The works for the construction of piles and the cap beam, as well as the temporary retaining of NIKEA Station, were completed, while waterproofing works of the foundation slab and the construction of prestressed anchors are in progress (levels 4 to 8);
  • The works for the construction of piles and the archaeological excavation were completed, while the excavation at levels 2 and 3 are in progress at the main building of MANIATIKA Station;
  • The worksite occupation for the PUO diversions, as well as the diversion of the gas pipe in OLP area at PIRAEUS Station are completed. Moreover, the investigation archaeological trenches for the identification of ISAP building sewage pipe were completed;
  • The relocation of PUO networks, as well as the installation of a building crane were completed, while the works for the construction of temporary retaining piles at Aghiou Konstantinou square, at DIMOTIKO THEATRO Station, are in progress;
  • The tunnel excavation has been completed to 5%.