May 2013

iso
  • The works for the PUO network diversions were completed in AGHIA VARVARA Station, while the worksite installations and the pile construction works for the temporary retaining of the Station are in progress;
  • The investigation trenches for the identification of the foundations of the Piraeus Port Authority S.A. (OLP) pedestrian bridge in PIRAEUS Station were completed;
  • The worksite occupation/fencing in Ag. Konstantinou Square at DIMOTIKO THEATRO Station is about to be completed soon along with the relocation of the last kiosks. In addition, the archaeological excavation works are in progress.