November 2014

  • NEW RAILWAY Station: The works related to the preparation of the modification of the traffic phase are at an advanced stage;
  • DIMOKRATIAS Station: The works for the removal of the metal propping of the northern roof slab has been completed;
  • AGHIA SOFIA Station: The works for the demolition of temporary structures in view of installing the 1st row of struts at the southern part of the Station have commenced;
  • SINTRIVANI Station: The excavation works at the 4th level (platform), the archaeological excavation works at the southern ventilation shaft and the works for the construction of walls and staircases inside the station are in progress;
  • PAPAFI Station: The works for the installation of the last row of struts, the works for the preparation of the traffic phase modification and the works for the construction of the western access are at an advanced stage;
  • EFKLIDIS Station: The works for the construction of the platform and the works for the installation of the escalators are at an advanced stage;
  • ANALIPSI Station & Crossover: The works for the construction of ventilation shaft 1 and of the eastern access are at an advanced stage;
  • PATRIKIOU Station & Crossover: The works for the construction of an underground strut implemented through jet grouting are in progress;
  • NEA ELVETIA Station & Crossover: The excavation and retaining works (prestressed anchors, shotcrete) at the station are at an advanced stage, while the waterproofing works have commenced;
  • DEPOT: The works for the construction of parapet walls and columns at the first floor of building I are in progress. Excavation, foundation and archaeological excavation works in the area surrounding building II are also in progress;
  • Tunnels: TBM assembly at NEA ELVETIA crossover is in progress, while the works for the construction of piles – cap beams, as well as the works for the diversion of PUOs at the C/C tunnel are at an advanced stage.