Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

September 2007

  • The archaeological excavations carried out on an overall surface of 5,000 m2 are at an advanced stage. Based on the archaeological study of the project, encountering antiquities on the section extending from NEOS SIDIRODROMIKOS STATHMOS (New Railway Station) to PANEPISTIMIO is very likely. An archaeological investigation has already been performed to more than 350 spots along the Line, while several significant finds have already come to light.
  • The works for the diversions of Public Utility Organizations (PUO) networks were completed in 5 worksite areas.
  • The construction of the start-up shaft for the two Tunnel Boring Machines (TBM) in NEOS SIDIRODROMIKOS STATHMOS is at an advanced stage.
Print Friendly, PDF & Email
WCAG