Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Νovember 2008

  • The assembly of the first Tunnel Boring Machine was completed.
  • The construction of diaphragm walls is at an advanced stage:
    • NEOS SIDIRODROMIKOS STATHMOS: completed at a percentage of 93%
    • DEMOKRATIAS Station: completed at a percentage of 76%
    • SYNTRIVANI Station: completed at a percentage of 91%
    • AGHIA SOFIA Station: completed at a percentage of 45%
    • Branching towards Stavroupoli: completed at a percentage of 72%
  • The construction of retaining piles at PANEPISTIMIO Station is at a completion phase: completed at a percentage of 81%.
Print Friendly, PDF & Email
WCAG