logo gr
logo en
Web Portal - Attiko Metro S.A.
ΑΤΤΙΚΟ ΜΕΤΡΟ Α.ΕΑΤΤΙΚΟ ΜΕΤΡΟ Α.ΕΑΤΤΙΚΟ ΜΕΤΡΟ Α.Ε
ΑΤΤΙΚΟ ΜΕΤΡΟ Α.ΕΑΤΤΙΚΟ ΜΕΤΡΟ Α.ΕΑΤΤΙΚΟ ΜΕΤΡΟ Α.Ε

June 2016

iso
  • NOMARCHIA Crossover: The works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert.
  • KALAMARIA Station: The installation of metal struts at the 2nd level have been completed. In progress are the excavation works and retaining works up to level -3.
  • ARETSOU Station: In progress are the works for the construction of reinforced concrete struts at the station roof level as well as the works for the construction of the piles cap beam for the temporary retaining.
  • NEA KRINI Station: The works for the construction of the Station’s northern access are in progress.
  • MIKRA Station & Crossover: The construction of piles for the temporary retaining is in progress.
  • MIKRA Forestation: In progress are works for the construction of piles for the temporary retaining and the cap beam. In progress are excavation and temporary retaining works at a section of the forestation.
  • End Shaft: In progress are construction works of the piles cap beam for the temporary retaining.
  • The preparation and approval of designs are in progress.
Print Friendly, PDF & Email
WCAG

Δομοστατική Καταγραφή Κτηρίων

για τη Νέα Γραμμή 4A