  • NOMARCHIA Station: The construction of struts made of reinforced concrete has been completed, while the excavation of the station’s level -1 is in progress;
  • NOMARCHIA Crossover: The construction of struts made of reinforced concrete has been completed, while the excavation of the crossover’s level -1 is in progress;
  • KALAMARIA Station: Works for the construction of perimeter piles at the southern-eastern section of the station have been completed. Works for the construction of perimeter piles cap beams and struts made of reinforced concrete are in progress in the same section. These works are also in progress in the northern-eastern section. Finally, the works for the construction of road surface and traffic barriers for the diversion of Pontou Street are in progress;
  • ARETSOU Station: Works for worksite installations are in progress;
  • NEA KRINI Station: Works for the waterproofing of the station and the construction of perimeter walls at level -1, platforms and part of the slab at level -1 are in progress;
  • MIKRA Forestation: Works for the boring of the 1st and the 2nd NATM tunnels, the excavation and the construction of the bottom slab in the TBM access shaft have completed;
  • MIKRA 2nd Crossover: Works for the construction of perimeter retaining piles and perimeter piles’ cap beams are in progress;
  • Terminal Shaft: The construction of perimeter piles has been completed;
  • Kritis shaft: The excavation of the 2nd phase has been completed; the installation of the 2nd level metal struts is in progress;
  • Pontou shaft: The construction of perimeter piles and perimeter piles cap beam has been completed;
  • The preparation and approval of designs are in progress;
  • The expropriation of areas in ARETSOU, MIKRA (part) Stations and MIKRA Forestation has been completed, while the supplementary expropriation of an area in a small part of MIKRA Station is still pending.