February 2015

  • NOMARCHIA Station & Crossover: The works for the diversion of the central sewage pipe have been completed. At an advanced stage are the works for the construction of a street parallel to Mitropoliti Kydonion Grigoriou Street within the area of the former Farmaki Military Camp, extending between G. Papandreou and V. Olgas Streets, as well as the works for the construction of a connecting road with Ifigenias Street. Moreover, the works for the diversion of PUO networks are at an advanced stage;
  • KALAMARIA Station: Preliminary works for the occupation of the worksite are have commenced. The works for the diversion of PUO networks are in progress, while the works concerning traffic arrangements are at an advanced stage;
  • NEA KRINI Station: The construction of the Station’s retaining works (pre-stressed anchors, cap beams/slabs retaining system) are at an advanced stage, while the excavation of the Station at a depth of approximately 9m is in progress;
  • MIKRA Station: The construction of temporary retaining works (prestressed anchors, bored piles, shotcrete) are at an advanced stage. Worksite installation works and TBM shaft excavation are in progress;
  • The preparation of designs is in progress;
  • The expropriation of spaces at ARETSOU Station, part of the MIKRA Station and at MIKRA Forestation is still pending.