Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

October 2015

  • In progress are the relocations of the following PUO networks: sewage and EPA at Vassileos Georgiou, EYDAP (water supply and sewage) networks at the sidewalk adjacent to Grigoriou Lambraki street, sewage and EPA networks at Omiridou Skylitsi street, OTE & fiber optics at Ethn. Antistaseos street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street. The works for the dismantling of trolley-bus networks at Vas. Georgiou & Ethn. Antistaseos streets have commenced and are in progress;
  • The archaeological excavation at the PUO relocation trenches on Grigoriou Lambraki and Vassileos Georgiou streets is in progress;
  • Trackwork construction works are in progress at Papandreou Bridge and on M. Asias Street, on Lambraki Street reversing and at Lambraki bridge. Earthworks have commenced and are in progress for the construction of Tramway stops on Mikras Asias street and at Gr. Lambraki bridge. Catenary poles foundation works have commenced and are in progress on Grigoriou Lambraki and Ethnikis Antistaseos Streets;
  • The urban planning work at the adjacent sidewalk of Mikras Asias and Ethnikis Antistaseos Streets are in progress. In the area where Akti Themistokleous and Zanni intersection is configured, the installation of underground waste bins and the relevant urban planning at 34th Syntagmatos Street are at the completion stage, while the urban planning at the sidewalk adjacent to Gr. Lambraki street (between Bouboulinas and Vas. Georgiou Streets) has been completed.
Print Friendly, PDF & Email
WCAG