Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

April 2017

NOMARCHIA Station: The permanent lining at level -1 has been completed. Works for the construction of the slab at level -2 are in progress.

• KALAMARIA Station: The construction of the permanent lining at level -3 has been completed. The construction of the slab at level -2 is in progress.

• ARETSOU Station: Permanent lining and waterproofing of level -3 have been completed. The construction of the slab at level -1 is in progress.

• NEA KRINI Station: The works for the construction of the northern entrance have been completed.

• MIKRA Station: Waterproofing and construction works of the perimeter walls at level -2 have been completed. The construction of the slab at level -1 and the platform are in progress.

• MIKRA Forestation: The construction of the invert at level 6 has been completed.

• TBM tunnels: The works for the assembly of the first Tunnel Boring Machine are in progress.

• Design preparation and approval are in progress.

Print Friendly, PDF & Email
WCAG