Project progress

Project progress

PROGRESS OF WORKS

AUGUST 2019

Α.            Tramway

  • Further to the completion of the works for the construction of the tramway the final tests – adjustments of the systems and devices controlling the operation of the Tramway system are still pending due to the suspension of the tramway vehicle trial runs on 19.07.2019 further to the blocking of a section of the tramway network at Omyrou Skylitsi Street due to an earthquake.
  • The E/M works at the new Substation 16 (Civil Works have been completed), as well as the upgrading of Substation 1 are pending.

Β.            OTHER WORKS (reference to extended work fronts)

  • Lambraki Bridge: Further to the completion of the concrete curing works, painting works have commenced and are in progress.
  • Further to the completion of the final tests, the underground waste bins have been delivered for use. The permanent electrification of some of them by the PCC is still pending.
  • Maintenance works and repair works for the reinstatement of minor deficiencies are being executed in all project structures.
Print Friendly, PDF & Email

JULY 2019

Α.            Tramway

  • Further to the completion of the works for the construction of the tramway (see previous progress of works), the final tests – adjustments of the systems and devices controlling the operation of the Tramway system (for integration of the extension to Piraeus into the basic network) and the adjustment – coordination of the circulation of the tramway vehicles with the road signage are in progress. The tramway vehicle trial runs were suspended on 19.07.2019 since a section of the tramway network at Omyrou Skylitsi Street was blocked further to an earthquake.
  • The E/M works at the new Substation 16 (Civil Works have been completed), as well as the upgrading of Substation 1 are pending.

Β.            OTHER WORKS (reference to extended work fronts)

  • Lambraki Bridge: Concrete curing works and staircases urban planning works have been completed. Painting works have commenced.
  • Platform located in Posidonos Avenue: The special lining of the floor (display of the underlying antiquities) and the works for the installation of the urban equipment (seats, etc.) have been completed.
  • Stops: The works for the installation of E/M equipment will soon be completed and final testing is in progress.
  • The installation of the foreseen lifts in the area of Lambraki Bridge and in the area of Karaiskaki stop has been completed (issuance of certification – license of operation in progress).
  • The final tests have been completed while the delivery for use of the remaining installed underground waste bins is in progress.