PROGRESS OF WORKS

October 2013

  • The performance of topographical works and investigation trenches in roads and sidewalks along the Tramway Extension to Piraeus, for the identification of archaeological finds and PUO networks, are in progress;
  • The dismantling works have been completed, while the works for the construction of walls intended for the re-configuration of the areas in Building No. 2 in the Tramway Depot Building facilities in ELLINIKO are in progress;
  • The earthwork landscaping in the land plot of the playground in the area of Rizareios – P. Faliro are in progress.
Print Friendly, PDF & Email

September 2013

  • The topographical works along the Tramway Extension to Piraeus are in progress;
  • The investigation trenches related works in roads and sidewalks along the Project, for the identification of archaeological finds and PUO networks, are in progress;
  • The Contractor has been installed in the land plot of Palaio Faliro Municipality in the area of Rizareios and the works for the configuration of a children’s garden have commenced. The works in the Tramway Depot Building facilities in ELLINIKO, where re-configuration of the areas and relevant repairs are in progress, have commenced.
Print Friendly, PDF & Email