The Metro Line 3 Extension to Piraeus, which is in an advanced stage of construction, includes a 7.6 km long tunnel and 6 new modern stations (Aghia Varvara, Korydallos, Nikaia, Maniatika, Piraeus and Dimotiko Theatro) as well as seven ventilation intershafts.

This is an investment rising to 730,000,000 euros in areas of the Municipality of Piraeus and other neighboring Municipalities (Nikaia, Korydallos, Aghia Varvara) , all of which are currently faced with acute traffic problems and low accessibility by the public transport modes.

On July 6, 2020, the first 3 stations of Aghia Varvara, Korydallos and Nikaia were commissioned. It is worth mentioning that these stations have been designed by Attiko Metro S.A. in a manner placing emphasis on bioclimatic characteristics and safe passenger trips in the Metro network

Upon commissioning of the first three stations of the Piraeus extension, the daily ridership on the entire network is expected to be increased by 63,000 passengers; at the same time, a modern Metro line shall be made available to the residents of the aforementioned three Municipalities.

The commissioning of the first 3 stations approximately 2 years earlier than the completion of the overall extension of the Metro Line 3 brings about significant socio-economic and other benefits, such the reduced carbon footprint and private vehicle circulation (less 60 tons of CO2 and 11,000 cars per day).

The entire Line 3 Extension is expected to be commissioned in summer 2022.

With the completion of the project and the commissioning of Maniatika, Piraeus and Dimotiko Theatro stations, the total ridership figure on the Metro network is foreseen be 132,000 passengers / day, thus reducing the circulation of private vehicles by 23,000 cars per day and the carbon dioxide emissions by 120 tons per day. It is pointed out that the distance from Piraeus Port to the Athens International Airport shall be covered by the Metro in just 55 minutes.

It is important to emphasize that with the completion of the project, a major Transport Center is foreseen to be developed at Piraeus Station, which shall functionally intergrade two Metro lines (Lines 1 and 3), the actual Port, the Suburban Railway and the Tramway Extension to Piraeus (5.4 km long single line and 12 stops), facilitating thus intermodal transfers.

In addition, the resulting connection between the Port of Piraeus and the Athens International Airport via the Metro Line 3, will foster growth in the greater area of Athens and Piraeus, with substantial benefits to the National Economy in general.

Print Friendly, PDF & Email

PROGRESS OF WORKS

MAY 2021

TZAVELLA SHAFT

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Construction of sound absorbing plaster.

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Completion of the permanent lining of the shaft.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Construction of shaft No. 4 at street level.
  • Masonry walls – plastering works at levels -4, -3, -2 and -1.
  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Industrial flooring at levels -4, -3, -2, -1.
  • Installation of ceramic tiles and granites at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.12.
  • Installation of doors.
  • Installation of ventilation grids.
  • Station backfilling.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Completion of the permanent lining of the station’s main tunnel.
  • Secondary concreting in platforms.
  • Installation of granites in platforms.

The following works are in progress:

  • Installation of false ceilings and side-covering panels.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Completion of the construction of the permanent lining.

The following works are in progress:

  • Installation of granites at the entrances of the staircases and at the cross-over tunnel.
  • Installation of items supporting the platforms’ metal lining at the upper transverse access tunnel.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Masonry walls – plastering works.
  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.

The following works are in progress:

  • Secondary staircase concreting works.
  • Architectural finishes (painting works).

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Pile cap beam demolition.
  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.

The following works are in progress:

  • Architectural finishes (painting works).

MELA SHAFT

The following works have been completed:

  • Concreting of the final lining of the NATM tunnel (vault + reverse arch).
  • Concreting of the pumping station roof

The following works are in progress:

  • Installation of reinforcement and concreting of the perimeter walls of the permanent lining.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Excavation and temporary retaining of entrances 1, 2 & 3.
  • Construction of architectural finishes (masonry walls, plastering at level -1, painting works at levels -1 and -3, industrial flooring, floor filling, floor screed concrete works, installation of ceramic tiles at level -1, metal doors at levels -2 and -3, filling laying works at levels -1 and -2, false-ceilings), area configuration works at ticketing level -1).
  • Laying of electrical insulation sheets at platform level.
  • Hydro-demolition of diaphragm walls between the station and the accesses 3.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Reinstatement works at street level.
  • Water proofing works at the roof of the shaft
  • Laying of industrial flooring.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station

The following works are in progress:

  • Backfilling – compaction works
  • Installation of doors at the platform the E/M levels
  • Installation of floor granite at the ticketing level and at the staircases
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining

The following works are in progress:

  • Installation of floor granite.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

The following works are in progress:

  • Installation of floor granite at the staircases.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete..

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining    

The following works are in progress:

  • Installation of floor granite at the connecting tunnel

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY

The following works have been completed:

  • Sealing of the temporary pumping station

The following works are in progress:

  • Reinstatement at street level

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Construction of permanent lining

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining
  • Waterproofing, construction of foundation slab and perimeter walls down to -3.0.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

  • Concreting of permanent lining of the shaft’s perimeter walls (completed up to +4.5)
Print Friendly, PDF & Email

APRIL 2021

TZAVELA SHAFT

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.

MANIATIKA STATION

STATION’s OPEN CUT

The following works have been completed:

  • Completion of the permanent lining of the shaft.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Construction of shafts 4 and 7 at street level.
  • Masonry walls – plastering works at levels -4, -3, -2 and -1.
  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Industrial flooring at levels -4, -3, -2, -1.
  • Installation of ceramic tiles at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.12.
  • Installation of doors.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Completion of the permanent lining of the station’s main tunnel.
  • Secondary concreting in platforms.
  • Installation of granites in platforms.

The following works are in progress:

  • Installation of items supporting the platforms’ metal lining.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Completion of the construction of the permanent lining of the station’s eastern lift.

The following works are in progress:

  • Installation of items supporting the platforms’ metal lining.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Masonry walls – plastering works.

The following works are in progress:

  • Surface reinstatement works.
  • Construction of perimeter wall at the expropriation boundaries.
  • Installation of metal structures at levels +8.36 and +21.00.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel. 

The following works are in progress:

  • Pile cap beam demolition.
  • Construction of perimeter wall at the expropriation boundaries.
  • Installation of metal structures at levels +8.08 and +24.98.

MELA SHAFT

The following works have been completed:

  • Concreting of the final lining of the NATM tunnel (vault + reverse arch).
  • Concreting of the foundation slab.

The following works are in progress:

  • Installation of reinforcement and concreting of the perimeter walls of the permanent lining.

PIRAEUS STATION 

The following works have been completed:

  • Concreting of the main station.

The following works are in progress:

  • Excavation and temporary retaining of entrance 1.
  • Excavation and temporary retaining of entrance 2.
  • Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, floor screed concrete works and installation of tiles at level -3, filling works at level -2, steel doors).
  • High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1).

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Slab cconcreting at level -7.50 (shed at the entry point of the connecting tunnel).
  • Sealing of the temporary pumping station.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Pile cap beam demolition.
  • Backfilling – compaction works at street level.
  • Installation of doors at the E/M floor, at the concourse level and at the platform level.
  • Installation of floor granite slabs at the platform level and at the concourse level.
  • Painting works at staircases 7 and 8.
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining.

The following works are in progress:

  • Installation of floor granites.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

The following works are in progress:

  • Installation of floor granite slabs at the southern staircase (landing at the concourse level).

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

The following works are in progress:

  • Construction of support system for wall-mounted granites in the access gallery.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY 

The following works have been completed:

  • Concreting of the permanent lining.

The following works are put on hold:

  • Backfilling – compaction related works.

The following works are in progress:

  • Construction of support system for wall-mounted granites in the access gallery
  • Secondary concrete in the area where the pebbled floor is exhibited.
  • Floor screed concrete works at the connecting tunnel.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS) & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.
  • Sealing of the temporary pumping station.

The following works are in progress:

  • Backfilling – compaction related works.
  • Construction of new sidewalks at street level.
  • Painting works at the shaft.
  • Construction of industrial floor for machinery pedestals.

DELIGIANNI SHAFT

 The following works have been completed:

  • Excavation and temporary retaining up to the final level
  • Waterproofing, construction of foundation slab and perimeter walls down to -3.0.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the foundation of the shaft’s permanent lining
  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

Concreting of the permanent lining of the shaft’s perimeter walls (completed up to level +4.5).

Print Friendly, PDF & Email