The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

PROGRESS OF WORKS

SEPTEMBER 2018

  • NEW RAILWAY Station: The works for the installation of E/M systems (fire extinguishing, water supply), as well as the construction of indoor partitions, are in progress.
  • DIMOKRATIAS Station (station and crossover): The works for the installation of doors at the station and well as painting works are in progress.
  • VENIZELOU Station: The works for burying antiquities within the main station box are in progress.
  • SINTRIVANI Station: The works for the construction of parapet walls in the surrounding area, at the north access, continue, while the works for the installation of E/M systems (water supply, sewage, fire fighting, fire detection, safety and intrusion detection system) are in progress.
  • PANEPISTIMIO Station: The E/M installation works (earthing, fire detection, telecommunications) are at an advanced stage, while painting works have commenced.
  • PAPAFI Station: The wall cladding works with granite slabs are at the completion stage, while the works related to the painting of the station and the shafts are at an advanced stage.
  • EFKLIDIS Station: Painting works at the platform level are in progress.
  • FLEMING Station:  Plastering activities on masonry walls is in progress.
  • ANALIPSI Station & Crossover: Flooring works are at an advanced stage, while painting works of the roof and the walls of the Station’s platform level continue.
  • 25 MARTIOU Station & Crossover: The construction of the staircase at the eastern emergency exit has been completed, while cladding works using granite slabs and works for the construction of industrial flooring continue.
  • VOULGARI Station: Works for the construction of balustrades at the emergency staircases are at an advanced stage.
  • NEA ELVETIA Station: Backfilling works, as well as cladding works with granite slabs are at an advanced stage.
Print Friendly, PDF & Email

AUGUST 2018

  1. Base Project
  • NEW RAILWAY Station: the configuration of the surrounding area is in progress.
  • DIMOKRATIAS Station (station and crossover): The works for the reinstatement of the south sidewalk of Monastiriou Street, as well as the subsequent traffic arrangement, are in progress.
  • VENIZELOU Station: The necessary works for the subsequent traffic arrangement have been completed, while in progress are the works for the installation of struts at the 1st and 2nd level of the eastern and western shafts, as well as the review of the structural, architectural and E/M designs.
  • AGHIA SOFIA Station: Archaeological excavation works and works for the deconstruction of finds at the south access have been completed, while in progress are the works for the installation of scaffoldings and formwork for the construction of the southern part of the station’s roof slab.
  • SINTRIVANI Station – EXPO: The works for the construction of parapet walls in the surrounding area, at the north access, are in progress.
  • PAPAFI Station: The works related to the painting of the station and the shafts are in progress.
  • EFKLIDIS Station: The configuration of the surrounding area is in progress.
  • ANALIPSI Station & Crossover: Painting works of the roof and the walls of the Station’s levels are in progress.
  • 25 MARTIOU Station & Crossover: The works for the construction of masonry walls and their plastering are in progress.
  • VOULGARI Station: Plastering works on masonry walls, as well as painting works, are in progress.
  • Depot – Building Complex I: E/M installation works are in progress, i.e. works related to cable trays, fire fighting, sewage, water supply.

Building Complex II: in progress is the construction of balustrades and marble cladding at the OCCs staircases and at building No. 9.