Project progress

Project progress

 

Thessaloniki Metro

Thessaloniki Metro is the largest transport, development and environmental infrastructure project currently under construction in our country, an investment exceeding 1.5 billion euros for the two lines under construction. Upon its completion, the city of Thessaloniki will become a modern European city, with a decisively improved urban landscape and living conditions for the citizens.

According to the Attiko Metro S.A. planning, the project is expected to be commissioned within 2023.

Thessaloniki Metro (Basic Project) consists of a 9.6 km long line, 13 modern stations and a 55,000m2 Depot in the area of Pylea.

There shall be 18 fully automatic driverless and air-conditioned trains of the latest technology, as well as automatic Platform Screen Doors in each station for improved passenger service and safety.

It is expected that upon completion of the project, the daily ridership shall rise to 313,000 passengers. In addition and as a result of the project’s operation, the number of the circulating private vehicles shall be reduced by 57,000 vehicles / day, and the respecting CO2 emissions shall be reduced by 212 tons per day

Given the project’s construction incorporates the most recent technologies and the most demanding standards of quality and functionality, Thessaloniki Metro will undoubtedly be the most modern Metro system in Europe.

Print Friendly, PDF & Email

PROGRESS OF WORKS

June 2021

  • NEW RAILWAY STATION: In progress are marble cladding works are at level -1, works for the installation of fire-rated air ducts at platform level and works for the redevelopment of the surrounding area at the north section of the station.
  • DIMOKRATIAS Station: In progress are works for the closing of the temporary opening of the roof slab.
  • AGHIA SOFIA Station: In progress are works for the construction of the sidewalk at the south section of Egnatia Street, works for the drilling of holes at platform level to install supports for the air ducts, and works for the installation of supports at the tunnel fire-fighting network towards VENIZELOU Station.
  • SINTRIVANI Station: Completed are works for the installation of fire-rated air ducts at platform level, works for the installation of TCR equipment, works for the installation of air ducts networks of the ventilation/air conditioning system in the technical area of the traction power supply equipment, as well as works for the installation of the lighting system in the tunnel. In progress are works for the construction of a wall at the north entrance and works for the installation of ventilation/air conditioning equipment in technical areas.
  • PANEPISTIMIO Station: Completed are works for the installation of signaling and lighting cables in the tunnel, as well as works for the installation of TCR equipment.
  • PAPAFI Station: In progress are works for the construction of a guard house and the fencing at Papafio Institution, works for the termination of TCR system cables and works for the installation of lighting system cables in the tunnel.
  • EFKLIDIS Station: Completed are installation and cabling works for the TCR system.
  • FLEMING Station: The works for the construction of the manhole connecting the water supply and the fire fighting networks of the station with EYATH (Thessaloniki Water Supply Company) at street-level have been completed. In progress are works for the termination of cables of the TCR system.
  • ANALISPI Station: The works for the electrical connection of escalators and the installation of the lighting system in the tunnel have been completed. In progress are works for the assembly and installation of fire-rated air ducts at platform level.
  • 25 MARTIOU Station: The works for the construction of the connection of the water supply and the fire fighting networks of the station with EYATH (Thessaloniki Water Supply Company) at street-level and the works for the installation of the radio communication system in the tunnel have been completed. In progress are works for the assembly and the installation of fire-rated air-ducts at the platform level, reinstatement works at street level and works for the installation of the fire-fighting system in the tunnel.
  • VOULGARI Station: In progress are works for the installation of the fire-fighting system equipment in the tunnel and works for the assembly and installation of necks for the fire-rated air ducts at the platform level.
  • NEA ELVETIA Station: Works for the installation of signaling cables have been completed. In progress are works for the termination of TCR cables and works for the assembly and installation of fire-rated air-ducts at platform level.

DEPOT

  • Building Complex Ι: In progress are works for the installation of signaling cables at level +52.00 of building 7 and works for the installation of the equipment of the rolling stock painting facilities at level +58.00.
  • Building Complex ΙI: In progress are building works, works for the installation of a false-ceiling in the Operation Control Centre, the installation of water supply network at level +66.40, the installation of the air conditioning network at level +59.00, works for the installation of doors and works for the installation of the lighting system at level +62.30 (OCC).
  • TRACKWORK: In progress are works for the installation of the 3rd rail at SINTRIVANI crossover, the installation of slabs at pedestrian walkways at the section between VOULGARI Station and the Depot, the installation of protective covers for the third rail and works for the installation of fire-fighting, signaling and lighting equipment in tunnels.
Print Friendly, PDF & Email

May 2021

  • New Railway Station: In progress are vertical marble cladding works at level -1, works for the installation of fire-rated air ducts at platform level, as well as works for the configuration of the surrounding area, at the north part of the station.
  • AGHIA SOFIA Station: In progress are masonry works at mezzanine and -1 levels, as well as plastering works at mezzanine level.
  • SINTRIVANI Station (Station and Crossover): In progress are reinstatement works at street level in the area of the School of Theology – Aristotle University of Thessaloniki, as well as works for the installation of fire-rated air ducts at platform level.
  • PANEPISTIMIO Station: The works for the installation of fire-rated air ducts at platform level have been completed, while reinstatement works at street level in the area of the University of Macedonia are in progress.
  • PAPAFI Station: Works related to the assembly and installation of fire rated ventilation air ducts at platform level have been completed.
  • EFKLIDIS Station: In progress are works for the installation of fire rated air ducts at platform level, as well as works for the configuration of the surrounding area.
  • FLEMING Station: In progress are works for the installation of fire rated air ducts at platform level, as well as works for the construction of the water supply and fire fighting manhole (connection with EYATH – Thessaloniki Water Company Property) at street level.
  • ANALIPSI Station: In progress are works for the installation of gypsum board on the metal sub-frame of the platform screen doors at track 1, works for the installation of signaling equipment in the tunnel, as well as works related to the termination of traction power cable.
  • 25 MARTIOU Station: In progress are works for the installation of trays, cables and earthing construction, as well as works for the construction of the water supply and fire fighting manhole (connection with EYATH – Thessaloniki Water Company Property) at street level.
  • VOULGARI Station: Completed are works for the assembly of fire rated air ducts at platform level, as well as works for the construction of the elevated floor in the traction power equipment area; in progress are works for the installation of platform screen doors, the construction of earthing at level -3 and the installation of cable trays at level -1.
  • NEA ELVETIA Station: Completed are excavation works for the routing of PPC supply cables in the station, as well as works for the construction of the elevated floor in the traction power equipment area.

 

DEPOT

Building Complex Ι: In progress are works for the installation of power distribution cables, works for the construction of earthing in the technical rooms of the substation, lighting and auxiliary power supply cables at level +52.00, as well as works for the installation of cable trays at level +69.00.

Building Complex ΙΙ: In progress are works for the installation of tiles at level +58.00, the installation of aluminium cladding and fire rated glass panels, the installation of A/C piping network at level +61.40 and the installation of CCU A/C units at levels +62.30 and +75.00. In the surrounding area, in progress are works for the construction of electromechanical networks and works for the construction of the routing of the sewage network.

TRACKWORK: The construction of the scissors crossover of Nea Elvetia crossover has been completed, while at the completion stage are the works for the construction of turnouts No. 26-27 and 28-29 at the tunnel section between NEA ELVETIA Station and the Depot. In progress is the construction of the scissors crossover at SINTRIVANI Crossover.

Moreover, in progress are works for the installation of 3rd rail at the section between NEA ELVETIA Station and the Depot, the installation of slabs at pedestrian walkways at the section between ANALIPSI and NEA ELVETIA Stations, the installation of protective covers for the 3rd rail at the section between PANEPISTIMIO and ANALIPSI Stations, as well as the works for the installation of signaling equipment, fiber optics and traction power cables in the tunnels.