Project progress

Project progress

 

Thessaloniki Metro

Thessaloniki Metro is the largest transport, development and environmental infrastructure project currently under construction in our country, an investment exceeding 1.5 billion euros for the two lines under construction. Upon its completion, the city of Thessaloniki will become a modern European city, with a decisively improved urban landscape and living conditions for the citizens.

According to the Attiko Metro S.A. planning, the project is expected to be commissioned within 2023.

Thessaloniki Metro (Basic Project) consists of a 9.6 km long line, 13 modern stations and a 55,000m2 Depot in the area of Pylea.

There shall be 18 fully automatic driverless and air-conditioned trains of the latest technology, as well as automatic Platform Screen Doors in each station for improved passenger service and safety.

It is expected that upon completion of the project, the daily ridership shall rise to 313,000 passengers. In addition and as a result of the project’s operation, the number of the circulating private vehicles shall be reduced by 57,000 vehicles / day, and the respecting CO2 emissions shall be reduced by 212 tons per day

Given the project’s construction incorporates the most recent technologies and the most demanding standards of quality and functionality, Thessaloniki Metro will undoubtedly be the most modern Metro system in Europe.

Print Friendly, PDF & Email

PROGRESS OF WORKS

April 2021

  • New Railway Station: Works for the configuration of the surrounding area, at the north part of the station are in progress.
  • DIMOKRATIAS Station: Granite installation works are in progress, at the staircases of the north and south access.
  • SINTRIVANI Station (Station and Crossover): The works for the electrical connections of the traction power supply system and the preparatory works for the reinstatement at street level are in progress. Works for the construction of the floating slab have been completed and the works for the construction of the scissors crossover are in progress.
  • PANEPISTIMIO Station: In progress are preparatory works for the reinstatement at street level, the installation of granite lining at the central staircase, as well as works for the installation of cables of the telecommunications system.
  • PAPAFI Station: Backfilling and surface reinstatement works are in progress.
  • EFKLIDIS Station: The works for the concreting of the temporary opening of the station’s roof slab have been completed, while works for the configuration of the surrounding area and works for the installation of optic fibers are in progress.
  • FLEMING Station: The works for the concreting of the temporary opening of the station’s roof slab have been completed, while works for the installation of cabling of the lighting system are in progress.
  • ANALIPSI Station: The works for the installation of platform screen doors have been completed, while in progress are works for the installation of the lighting system and of cables of the telecommunications system.
  • 25 MARTIOU Station: Works for the installation of signaling equipment at track level are in progress.
  • VOULGARI Station: In progress are works for the assembly of fire rated air ducts at platform level, as well as works for the installation of signaling equipment and fiber optics.
  • NEA ELVETIA Station: In progress are works for the lining of staircases with granite slabs, the installation of equipment of the data transmission system, the installation of cables of the fire detection system, as well as the installation of signaling cables.

DEPOT

Building Complex Ι: In progress are works for the installation of cables of the telecommunication system and of the access control and intrusion detection system at level +74.00, works for the installation of power supply cables, as well as works for the installation of cables of the BACS system.

Building Complex ΙΙ: In progress are works for the installation of gypsum boards at level +58.00, the installation of water supply pipes at level +66.40, A/C and fire fighting pipes at level +55.45, as well as works for the installation of the access control and intrusion system at level +58.00.

TRACKWORK: In progress are rail welding works at turnout 26-27, works for the installation of 3rd rail at the section between ANALIPSI and 25 MARTIOU Stations, the installation of slabs at pedestrian walkways at the section between PAPAFI and EFKLIDIS Stations, the installation of equipment of the data transmission system at the section between VOULGARI Station and the Depot, as well as the radio communication system between SINTRIVANI  Station and the Depot.

Print Friendly, PDF & Email

March 2021

 

  • New Railway Station: Works for the installation of cable trays at the signaling and telecommunications technical rooms have been completed. Works for the installation of equipment of the fire fighting system in tunnels are in progress.
  • DIMOKRATIAS STATION: Works related to the installation of the air ducts network at level -1 have been completed. Works for the configuration of the surrounding area at the northern sidewalk of the station are in progress.
  • SINTRIVANI Station (Station and Crossover): The works for the concreting of the temporary openings (eastern and western) at level -3 of the Crossover have been completed.
  • PANEPISTIMIO Station: Works for the installation of signalling cables, as well as works for the installation of lifts are in progress.
  • PAPAFI Station: Works for the assembly and installation of necks of fire rated ventilation air ducts at platform level are in progress.
  • FLEMING Station: Equipment cabling related works in the technical area of the control panels of the platform screen doors are in progress.
  • ANALIPSI Station: The works for the installation of signaling equipment in the tunnels are in progress.
  • VOULGARI Station: In progress are works for the installation of fire rated air ducts at track level and for the installation of the metal structure of the platform screen doors (track 2).
  • NEA ELVETIA Station: Excavation works for the routing of PPC supply cables in the station are in progress.

DEPOT

Building Complex Ι: In progress are works for the installation of BACS cables at level +58.00 and for the installation of cable trays at level +52.00, at building 5.

Building Complex ΙΙ: Works for the installation of water pipes at level +66.40 are in progress.

TRACKWORK: The works for the construction of the floating slab/turnover 26-27 at the tunnel leading to the Depot have been completed. The works for the installation of turnover 26-27 and turnover 28-29 are in progress. Moreover, in progress are the works for the installation of the 3rd rail, the installation of cable trays, as well as alignment related works and works for the installation of signalling and telecommunications related equipment between PANEPISTIMIO Station and the Depot.