Project progress

Project progress

 

Thessaloniki Metro

Thessaloniki Metro is the largest transport, development and environmental infrastructure project currently under construction in our country, an investment exceeding 1.5 billion euros for the two lines under construction. Upon its completion, the city of Thessaloniki will become a modern European city, with a decisively improved urban landscape and living conditions for the citizens.

According to the Attiko Metro S.A. planning, the project is expected to be commissioned within 2023.

Thessaloniki Metro (Basic Project) consists of a 9.6 km long line, 13 modern stations and a 55,000m2 Depot in the area of Pylea.

There shall be 18 fully automatic driverless and air-conditioned trains of the latest technology, as well as automatic Platform Screen Doors in each station for improved passenger service and safety.

It is expected that upon completion of the project, the daily ridership shall rise to 313,000 passengers. In addition and as a result of the project’s operation, the number of the circulating private vehicles shall be reduced by 57,000 vehicles / day, and the respecting CO2 emissions shall be reduced by 212 tons per day

Given the project’s construction incorporates the most recent technologies and the most demanding standards of quality and functionality, Thessaloniki Metro will undoubtedly be the most modern Metro system in Europe.

Print Friendly, PDF & Email

PROGRESS OF WORKS

April 2020

NEW RAILWAY STATION: The works for the construction of the filling concrete in the area of the forestation are in progress.

DIMOKRATIAS Station: The works for the installation of a sewage network are in progress.

VENIZELOU Station: The works for the removal of struts and monorail installation are in progress.

PANEPISTIMIO Station: The works for the installation of gas equipment in tunnels are in progress.

EFKLIDIS Station: The works for the installation of a third rail in track 1 are in progress.

NEA ELVETIA Station: The works for the reinstatement of escalators are in progress.

DEPOT:

Building Complex Ι: The works for the construction of tiles at the washing plant have been completed. Works for the configuration of the surrounding area are in progress.

Building Complex ΙΙ: The installation of lifts 2.2 has been completed while the installation of the water supply network is in progress.

ΤΒΜ Tunnels: Trackwork construction works in a section of the project tunnels are in progress.

Print Friendly, PDF & Email

March 2020

NEW RAILWAY Station: In progress are the works related to the installation of the sewage network at level -2, as well as the works for the construction of the Forestation platform.

DIMOKRATIAS Station: The works for the installation of fire-rated air ducts of the tunnel ventilation system have been completed and in progress are the works for the installation of the automatic fire extinguishing system.

VENIZELOU Station: In progress are the preparatory works for the removal of struts.

AGHIAS SOFIAS Station: The construction of the station connections with the tunnels has been completed. In progress are the works for the construction of walls and of the top of the SW shaft, as well as works related to the water tightness of diaphragm walls.

SINTRIVANI Station: In progress are installation works and works related to connections of the tunnel ventilation equipment.

PANEPISTIMIO Station: In progress are the works related to the electric connections of escalators.

PAPAFI Station: In progress are the installation of tunnel ventilation equipment and the installation of lighting cables at track 1 tunnel.

ANALIPSI Station (Station and Crossover): In progress are the works for the installation of lighting cable ducts at the platform.

25TH MARTIOU Station (Station and Crossover): Lift installation works are in progress.

DEPOT:

Building Complex Ι: In progress are works for the construction of tiles at the washing plant, the installation of roller shutters, at levels +52 and +58, as well as the works for the installation of signalling and A/C network cables.

 Building Complex ΙΙ: In progress are the works for the construction of gypsum boards, the installation of the fire fighting network, the A/C network, the installation of cable trays, of the lightning protection, as well as the installation of lifts.

TBM tunnels: The construction of trackwork at a specific section of the Project tunnels is in progress.

Print Friendly, PDF & Email