Project progress

Project progress

The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

Print Friendly, PDF & Email

PROGRESS OF WORKS

OCTOBER 2018

  • NEW RAILWAY Station: The works for the construction of indoor partitions are in progress.
  • DIMOKRATIAS Station (Station and Crossover): The works for closing the southern opening, as well as for the reinstatement of the southern sidewalk of Monastiriou street are in progress. Works related to the implementation of the next traffic arrangement at the Crossover have commenced.
  • VENIZELOU Station: Archaeological survey related works at the west and east shafts are in progress.
  • AGHIA SOFIA Station: Completed is the construction of the southern part of the roof slab, as well as the construction of micro-piles within the north access outline. Works for the removal of struts at level -1 of the station are in progress.
  • SINTRIVANI Station: Wall cladding works with granite slabs, painting and plastering works are at an initial stage, while the works for the installation of E/M systems are at an advanced stage.
  • PANEPISTIMIO Station: Wall cladding works with granite slabs have commenced.
  • PAPAFI Station: Painting works continue, while wall cladding works with granite slabs are in progress.
  • EFKLIDIS Station: Painting works continue, while gypsum board construction works are in progress.
  • FLEMING Station: Wall cladding works with granite slabs, as well as E/M installation works are in progress.
  • 25 MARTIOU Station & Crossover: E/M systems and door installation works are in progress.
  • VOULGARI Station: Painting works, as well as E/M installation works are in progress.
  • NEA ELVETIA Station: Wall cladding works with granite slabs continue, while E/M installation works have commenced.
    • Depot: The works for the construction of networks and shafts in the testing track area have been completed.
      • Building Complex Ι: The works for the installation of door frames and cladding of facades are in progress.
      • Building Complex ΙΙ: The works for the installation of E/M systems and the construction of trackwork are in progress.
    • ΤΒΜ tunnels: The works for the construction of pumping stations are in progress.
Print Friendly, PDF & Email

SEPTEMBER 2018

  • NEW RAILWAY Station: The works for the installation of E/M systems (fire extinguishing, water supply), as well as the construction of indoor partitions, are in progress.
  • DIMOKRATIAS Station (station and crossover): The works for the installation of doors at the station and well as painting works are in progress.
  • VENIZELOU Station: The works for burying antiquities within the main station box are in progress.
  • SINTRIVANI Station: The works for the construction of parapet walls in the surrounding area, at the north access, continue, while the works for the installation of E/M systems (water supply, sewage, fire fighting, fire detection, safety and intrusion detection system) are in progress.
  • PANEPISTIMIO Station: The E/M installation works (earthing, fire detection, telecommunications) are at an advanced stage, while painting works have commenced.
  • PAPAFI Station: The wall cladding works with granite slabs are at the completion stage, while the works related to the painting of the station and the shafts are at an advanced stage.
  • EFKLIDIS Station: Painting works at the platform level are in progress.
  • FLEMING Station:  Plastering activities on masonry walls is in progress.
  • ANALIPSI Station & Crossover: Flooring works are at an advanced stage, while painting works of the roof and the walls of the Station’s platform level continue.
  • 25 MARTIOU Station & Crossover: The construction of the staircase at the eastern emergency exit has been completed, while cladding works using granite slabs and works for the construction of industrial flooring continue.
  • VOULGARI Station: Works for the construction of balustrades at the emergency staircases are at an advanced stage.
  • NEA ELVETIA Station: Backfilling works, as well as cladding works with granite slabs are at an advanced stage.
Print Friendly, PDF & Email