Extension to Kalamaria

Extension to Kalamaria

The Expansion to Kalamaria, which is already in an advanced construction phase, includes 5 new Stations (Nomarchia, Kalamaria, Aretsou, Nea Krini and Mikra) located along an underground line 4.78 km long.

It is expected that upon completion of the project, the daily ridership shall rise to 63,000 passengers. In addition and as a result of the project’s operation, the number of the circulating private vehicles shall be reduced by approximately 12,000 vehicles / day, and the respecting CO2 emissions shall be reduced by 43 tons per day. The distance between Mikra Station and the center of the city shall be covered in just 15 minutes

This project will undoubtedly upgrade Kalamaria Municipality in terms of transport services and the environment, while it shall also substantially improve the quality of the citizens’ daily lives.

Print Friendly, PDF & Email

PROGRESS OF WORKS

January 2021

  • NOMARCHIA Station (Station and Crossover): Reinstatement related works at street level, as well as works for the installation of galvanized balustrades are in progress.
  • KALAMARIA Station: In progress are works for the installation of glass panels of the sheds at the west entrance, as well as works for the installation of cabling for the lighting networks.
  • NEA KRINI Station: In progress are works for the installation of the fire fighting system.

TRACKWORK: Concreting works at tracks 1 and 2 from K.P. 2+800 to KALAMARIA Station have been completed, while in progress are the respective works at tracks 1 and 2 from KALAMARIA Station to NOMARCHIA Crossover.

Print Friendly, PDF & Email

December 2020

  • Kritis Shaft: Reinstatement related works at street level, painting works and works related to the completion of door installation are in progress.
  • KALAMARIA Station: In progress are reinstatement related works at street level, as well as works for the installation of glass panels of the sheds at the east entrance.
  • ARETSOU Station: In progress are works for the installation of trays, as well as works for the installation of cabling for the lighting networks.
  • MIKRA Station: Surface reinstatement works are in progress.

 

TRACKWORK: Concreting works at tracks 1 and 2, from K.P. 0+091 to Nomarchia Crossover have been completed, while in progress are the respective works at tracks 1 and 2, from K.P. 2+800 to KALAMARIA Station.