Extension to Kalamaria

Extension to Kalamaria

The Expansion to Kalamaria, which is already in an advanced construction phase, includes 5 new Stations (Nomarchia, Kalamaria, Aretsou, Nea Krini and Mikra) located along an underground line 4.78 km long.

It is expected that upon completion of the project, the daily ridership shall rise to 63,000 passengers. In addition and as a result of the project’s operation, the number of the circulating private vehicles shall be reduced by approximately 12,000 vehicles / day, and the respecting CO2 emissions shall be reduced by 43 tons per day. The distance between Mikra Station and the center of the city shall be covered in just 15 minutes

This project will undoubtedly upgrade Kalamaria Municipality in terms of transport services and the environment, while it shall also substantially improve the quality of the citizens’ daily lives.

Print Friendly, PDF & Email

PROGRESS OF WORKS

November 2020

  • Kritis Shaft: Coloring works and works related to the completion of door installation are in progress.
  • NOMARCHIA Station: In progress are preliminary reinstatement related works at street level, as well as works for the installation of cabling for the lighting network.
  • ARETSOU Station: Infrastructure construction works for irrigation and fire-fighting networks have been completed.
  • Pontou Shaft: Coloring works are in progress.
  • NEA KRINI Station: Infrastructure construction works for irrigation and fire-fighting networks have been completed.
  • TRACKWORK: In progress are works for the installation of trunkways – walkways from the area of the Forestation up to NEA KRINI Station.
Print Friendly, PDF & Email

October 2020

KALAMARIA Station: Landing paving works at the staircase of the eastern entrance and works for the installation of scaffoldings for the installation of glass panels at the sheds of the eastern and western entrances are in progress. In progress are also works for the installation of earthing and cabling for lighting networks.

ARETSOU Station: Infrastructure construction works for irrigation and fire-fighting networks, painting works in public areas and painting works of galvanized balustrades in technical rooms are in progress.

Pontou Shaft: Works for the construction of industrial flooring have been completed.

NEA KRINI Station: In progress are works for the installation of sound panels.

Terminal Shaft: In progress are works for the installation of galvanized balustrades

TRACKWORK

Moreover, concreting works on tracks 1 & 2 from K.P. 0+0.91 up to Nomarchia Crossover and the installation of precast ducts on the sidewalks of track 1 from K.P. 2+800 up to the 2nd Crossover have been completed.