Piraeus Project progress

December 2012

Excavation works in the Tunnel Boring Machine (TBM) startup shaft have commenced. Signaling works for the implementation of traffic arrangements at KORYDALLOS Station are in progress.
Read More

November 2012

The construction of retaining piles in the TBM startup shaft has been completed and excavation works are in progress. All works related to the dismantling of various items, relocations of kiosks and transplantations have been completed in the six (6) stations of the Project and the archaeological survey, as well as the PUO network diversions, […]
Read More

October 2012

The pile driving works at the TBM Start-up Shaft have been completed; The relocation of the Public Utility Organizations networks is in progress at AGHIA VARVARA Station; The archaeological survey is in progress at AGHIA VARVARA, NIKEA, KORYDALLOS and DIMOTIKO THEATRO Stations; The worksite occupation related works are in progress at Odyssos Square (PIRAEUS Station) […]
Read More

September 2012

The works for the construction of temporary retaining piles in the TBM access shaft are in progress; The archaeological survey in KORYDALLOS Station area is at an advanced stage; The worksite installation of the Contractor in MANIATIKA Station area has been completed; The works for the relocation of the kiosks located within the construction boundaries […]
Read More

August 2012

The archaeological excavation in the TBM start up shaft in the area of Aghia Varvara is completed; The dismantling and transplantation works, as well as the execution of investigation trenches for PUO networks in AGHIA VARVARA, NIKEA and KORYDALLOS Stations are at an advanced stage; The work site occupation of the Contractor in DIMOTIKO THEATRO […]
Read More

July 2012

The archaeological investigation at the Start-up Shaft of the Tunnel Boring Machine (TBM) in the area of Aghia Varvara is in progress. The worksite occupation in KORYDALLOS and NIKEA Stations is in progress. The Supplementary Boreholes Plan along the Metro Extension to Piraeus has been completed.
Read More

June 2012

The worksite occupation in the area of Aghia Varvara has commenced from where the Tunnel Boring Machine will start its journey with direction to Piraeus. The boreholes’ program along the extension to Piraeus is at a completion stage.
Read More

May 2012

The complementary boreholes campaign along the Metro Extension to Piraeus is in progress.
Read More

April 2012

ATTIKO METRO S.A. in cooperation with the Joint Venture J&P Αβαξ S.A. — Ghella SpA — Alstom Tranport S.A. is performing all necessary survey works for the construction of the Metro Extension to Piraeus.
Read More