Thessaloniki Base Project progress

June 2008

The execution of piling works is in progress (completed at a percentage of 35%) at the entrances/exits of VENIZELOS Station, while respective works at AGHIA SOFIA Station commenced. Archaeological finds were revealed at the southeastern side of SINTRIVANI Station. The excavation of the start-up shaft of the TBM in the area of NEOS SIDIRODROMIKOS STATHMOS […]
Read More

May 2008

The construction of diaphragm walls at SINTRIVANI Station (completed at a percentage of 55%) and at DEMOKRATIAS Station (completed at a percentage of 35%) is at an advanced stage, while the installation of piles at the entrances/exits of VENIZELOS Station commenced. Worksite installation of the contracting consortium at PAPAFI Station is in progress. The construction […]
Read More

April 2008

The second Tunnel Boring Machine arrived in Thessaloniki. Diaphragm walls at VENIZELOU Station were completed and works related to the installation of the metal bridge at the street level commenced. Works related to the excavation of the forestation at NEOS SIDIRODROMIKOS STATHMOS commenced. The excavation of the start-up shaft of the tunnel boring machine in […]
Read More

Μarch 2008

The construction of diaphragm walls at VENIZELOS Station (completed at a percentage of 98%),at SYNTRIVANI Station (completed at a percentage of 48%) as well as at DEMOKRATIAS Station (completed at a percentage of 12%) is in progress. Works related to the diversion of the non-fire resistant pipe at AGHIA SOFIA Station are at an advanced […]
Read More

February 2008

The main construction works at VENIZELOS and SYNTRIVANI Stations are in progress. Works related to the diversion of the non-fire resistant pipe at AGHIA SOFIA Station are in progress. PUO works in the area of PANEPISTIMIO Station are in progress and the worksite occupation of EFKLEIDIS Station commenced. The excavation of the start-up shaft of […]
Read More

January 2008

The works for the construction of D-walls have started at the south side of VENIZELOU Station. The excavation of the TBM start-up shaft is in progress. The worksite occupation at PANEPISTIMIO station has commenced while new worksites will be soon installed at EFKLIDI and FLEMING Stations.
Read More

December 2007

The construction of the diaphragm walls on the northern side of VENIZELOU Station was completed and early next year relevant works will commence to be executed on the southern side of the Station. The construction of diaphragm walls commenced at the Branching of the extension to Stavroupoli in the area of DEMOKRATIAS Station. PUO network […]
Read More

November 2007

One of the two TBMs arrived at Thessaloniki on Monday, November 30. The second one is expected to arrive in the beginning of 2009.
Read More

October 2007

The construction of Neos Sidirodromikos Stathmos station and Sidrivani station commenced. The construction of the diaphragm walls is in progress in Neos Sidirodromios Stathmos, whereas in Sidrivani station piling works in the north part of the station has been completed, while the construction of diaphragm walls commenced. The works for the diversions of Public Utility […]
Read More

September 2007

The archaeological excavations carried out on an overall surface of 5,000 m2 are at an advanced stage. Based on the archaeological study of the project, encountering antiquities on the section extending from NEOS SIDIRODROMIKOS STATHMOS (New Railway Station) to PANEPISTIMIO is very likely. An archaeological investigation has already been performed to more than 350 spots […]
Read More