OCTOBER 2019
DOUBLE TRACK ΝΑΤΜ START TUNNEL Works have been completed. KOMNINOU SHAFT The following works have been completed: Masonry works, plastering works, door installation, industrial floor, painting works, installation of grids at street level, staircase balustrades, hatch Reinstatement at street level AGHIA VARVARA STATION The following works are in progress: Reinstatement at street level – Square […]