Thessaloniki Base Project progress

February 2021

  New Railway Station: Works for the installation of cable trays at the signaling and telecommunications technical rooms are in progress. DIMOKRATIAS STATION: Works related to the installation of the air duct networks at level -1 are in progress. VENIZELOU Station: Archaeological excavations are in progress at the southern entrance. SINTRIVANI Station (Station and Crossover): […]
Read More
ΒΑΣΙΚΟ ΕΡΓΟ - ΙΑΝΟΥΑΡΙΟΣ 2021

January 2021

    DIMOKRATIAS STATION: Works related to the installation of fire fighting, sewage and water supply networks at level -2 have been executed. AGHIA SOFIA Station: Preparatory works for the construction of masonry at levels -2 and -3 are in progress. SINTRIVANI Station: The works for the installation of sub-frames to support the platform air […]
Read More
THESSALONIKI_12_20

December 2020

  NEW RAILWAY STATION: Works related to the construction of masonry walls and plastering related works have been executed. VENIZELOU Station: The works for the removal of the equipment and installations at the south access have been completed. AGHIA SOFIA Station: Works for the construction of parapet walls’ terminations at the south access, as well […]
Read More

November 2020

  DIMOKRATIAS Station: In progress are works for the installation of the air duct network at level -2. VENIZELOU Station: Diaphragm walls construction works at the southern access, as well as works related to roof slab supporting piles have been completed. AGHIA SOFIA Station: Works for the construction of parapet walls’ terminations at the south […]
Read More
Πρόοδος Βασικού Έργου Θεσσαλονίκης - Οκτώβριος 2020

October 2020

  VENIZELOU Station: Diaphragm walls construction works at the southern access have been completed. In progress are equipment and related facilities removal works, as well as works for the construction of temporary retaining piles at the southern access. AGHIA SOFIA Station:  Surface reinstatement works at the south section of the station are in progress. PANEPISTIMIO […]
Read More
Πρόοδος βασικού έργου Θεσσαλονίκης - Σεπτέμβριος 2020

September 2020

  NEW RAILWAY Station: Works for the installation of E/M equipment bases and works for the installation of sewage and fire fighting networks have been executed. DIMOKRATIAS Station: Works for the installation of E/M equipment bases have been executed. AGHIA SOFIA Station: Works for the construction of the permanent lining of the southern access, as […]
Read More
Πρόοδος βασικού έργου Θεσσαλονίκης - Αύγουστος 2020

August 2020

  DIMOKRATIAS Station: The works for the reinstatement of the indoor and outdoor elevator have been executed. AGHIA SOFIA Station: The works for the construction of the permanent lining of the southern access as well as the works for the construction of masonry walls in the technical rooms and the network relocation works are in […]
Read More

July 2020

  NEW RAILWAY STATION: The works for the configuration of the surrounding area at the north part of the station are in progress. VENIZELOU Station: The works for the construction of the guide rails of the southern access diaphragm walls and the works for the relocation of sewage networks are in progress. AGHIA SOFIA Station: […]
Read More

June 2020

NEW RAILWAY STATION: The works for the transport and distribution of rail-tracks are in progress. DIMOKRATIAS Station: The works for the transport and distribution of rail-tracks are in progress. VENIZELOU Station: The works for cutting the walls to encase the temporary backfill, as well as the preliminary works for the construction of the rails of […]
Read More

April 2020

NEW RAILWAY STATION: The works for the construction of the filling concrete in the area of the forestation are in progress. DIMOKRATIAS Station: The works for the installation of a sewage network are in progress. VENIZELOU Station: The works for the removal of struts and monorail installation are in progress. PANEPISTIMIO Station: The works for […]
Read More