Piraeus Project progress

APRIL 2019

– TBM access shaft: The waterproofing of the ceiling slab +62.86 has been completed. – Komninou shaft: The works for the staircase balustrade have been completed, while architectural works (hatch construction) are in progress. AGHIA VARVARA Station: The works for the installation of granite slabs on the floor and walls…
Μάθε Περισσότερα

MARCH 2019

– TBM access shaft: The installation of an indoor steel plate has been completed. – Komninou shaft: Surface reinstatement is in progress. – Megalou Alexandrou shaft: Surface reinstatement is in progress. – Pissidias shaft: The final lining of Pissidias Shaft has been completed, screed placing at the treads of the…
Μάθε Περισσότερα

FEBRUARY 2019

Piraeus TBM access shaft: The construction of slabs at levels +47.46 and +56.11 has been completed, while the surface reinstatement is in progress. Komninou shaft: The installation of a grid at street level has been completed, while the architectural works (manufacturing of balustrades) are in progress. AGHIA VARVARA station: The…
Μάθε Περισσότερα

JANUARY 2019

  TBM access shaft: the construction of slabs at level +47.46 has been completed, while the waterproofing of the roof slab at level +62.86 and the construction of parts of slabs at levels +56.11, +62.86 are in progress.   Komninou Shaft: Painting works have been completed, while the remaining architectural…
Μάθε Περισσότερα

DECEMBER 2018

Komninou Shaft: Architectural works are in progress. AGHIA VARVARA Station: The wall cladding works and the works for the installation of columns have been completed, while the works for the installation of false ceiling system supports at the ticketing level are in progress. Meg. Alexandrou Shaft: Architectural works are in…
Μάθε Περισσότερα

NOVEMBER 2018

Komninou Shaft: Architectural works are in progress. AGHIA VARVARA Station: At ticketing level walls, at the staircases and the landings the works for the installation of granite slabs are in progress. Meg. Alexandrou Shaft: Completed are masonry and plastering works, as well as the works for the installation of doors…
Μάθε Περισσότερα

OCTOBER 2018

TBM Access Shaft: The works for the waterproofing of the perimeter walls have been completed. Komninou Shaft: The works for the excavation and temporary retaining of the shaft and the connecting tunnel, as well as the works related to masonry, cladding, installation of doors and industrial floors have been competed.…
Μάθε Περισσότερα

SEPTEMBER 2018

Two-track NATM tunnel: The works for the permanent lining of the tunnel’s vault have been completed. TBM Access Shaft: The works for the excavation and temporary retaining of the shaft have been completed together with the works for the construction of the foundation slab and the perimeter walls. Komninou Shaft:…
Μάθε Περισσότερα

AUGUST 2018

KORYDALLOS Station: In progress are the works for the waterproofing and permanent lining of the station’s accesses, as well as the works for the installation of doors, metal panels and the dismantling of piles and cap beams. Pissidias shaft: In progress are the works for the construction of the final…
Μάθε Περισσότερα

June 2018

• Komninou Shaft: The works for the construction of a staircase is in progress. • AGHIA VARVARA Station: In progress are the preliminary activities for the commencement of the architectural works in M. Alexandou Shaft. At recess 4+867, the works for the installation of the metal structure in the TBM…
Μάθε Περισσότερα