Year: 2019

FEBRUARY 2019

Piraeus TBM access shaft: The construction of slabs at levels +47.46 and +56.11 has been completed, while the surface reinstatement is in progress. Komninou shaft: The installation of a grid at street level has been completed, while the architectural works (manufacturing of balustrades) are in progress. AGHIA VARVARA station: The…
Μάθε Περισσότερα

FEBRUARY 2019

As regards the TRAMWAY NETWORK The works for the construction of the Tramway corridor have been completed (trackwork – rails – catenary) have been completed. The trial run of the Tramway system commenced, while checking – arrangements – tests of the Tramway and catenary related installations are at the completion…
Μάθε Περισσότερα

JANUARY 2019

As regards the TRAMWAY NETWORK The works for the construction of the Tramway corridor have been completed (trackwork – rails – catenary) have been completed. The checking – arrangements – tests of the Tramway and catenary related installations are at the completion stage, while the trial running of the Tramway…
Μάθε Περισσότερα

JANUARY 2019

  TBM access shaft: the construction of slabs at level +47.46 has been completed, while the waterproofing of the roof slab at level +62.86 and the construction of parts of slabs at levels +56.11, +62.86 are in progress.   Komninou Shaft: Painting works have been completed, while the remaining architectural…
Μάθε Περισσότερα

January 2019

NOMARCHIA Station: Architectural works and works for the installation of E/M systems are in progress. KALAMARIA Station: The works for the construction of the east access, as well as the architectural and E/M installation works are in progress. ARETSOU Station: Architectural and E/M installation works are in progress. NEA KRINI…
Μάθε Περισσότερα
eikona palia 1

DECEMBER 2018

OTHER WORKS (reference to extensive fronts of works) Along the Tramway route in Piraeus Seven (7) out of the eleven (11) power supply connections of the Tramway stops with the PPC network have been completed. The works for the installation of urban fittings are at the completion stage, while the…
Μάθε Περισσότερα

DECEMBER 2018

NOMARCHIA Station: Floor cladding works using granite slabs are in progress, while E/M installation works are at an initial stage. KALAMARIA Station: Painting works are at an initial stage, while works for the construction of the platform and the construction of the north ventilation shaft have commenced. ARETSOU Station: Floor…
Μάθε Περισσότερα

DECEMBER 2018

NEW RAILWAY Station: The works for the installation of ceramic tiles continue. DIMOKRATIAS Station (Station and Crossover): The reinstatement of the southern sidewalk at Monastiriou street (at the crossover), as well as the implementation of traffic phase L’ have been completed. Floor cladding works using granite slabs are in progress.…
Μάθε Περισσότερα