Year: 2020

MARCH 2020

  AGHIA VARVARA STATION The following works are in progress: Wall and columns cladding (metal, glass etc.) Square reinstatement (granites, passageways) Signage, signalling and lighting Other reinstatement works at street level Station signs and other signs. MEGALOU ALEXANDROU SHAFT The following works are still pending: Planting (street level). TAXIARCHON SHAFT…
Μάθε Περισσότερα

FEBRUARY 2020

  AGHIA VARVARA STATION The following works are in progress: Installation of lifts in the station Wall and columns cladding (metal, glass etc.) Installation of balustrades Installation of handrails Other architectural finishes Installation of a fountain Planting and irrigation system Installation of false ceilings at the ticketing level Square reinstatement…
Μάθε Περισσότερα
Ξενάγηση εκπροσώπων του Εμπορικού Συλλόγου Θεσσαλονίκης σε εργοτάξια του Μέτρο

Thessaloniki Metro: Visit of Thessaloniki Traders Association Representatives at the worksites of Thessaloniki Metro

During the meeting held today with the Chairman and members of Thessaloniki Traders Association, Mr. Nikolaos Tachiaos, Chairman of ATTIKO METRO S.A BoD, expressed his reassurance that the works for the construction of Thessaloniki Metro are progressing at a fast pace and that the project could be commissioned early 2023.…
Μάθε Περισσότερα

JANUARY 2020

  AGHIA VARVARA STATION The following works are in progress: Installation of lifts in the station Wall and columns cladding (metal, glass etc.) Installation of handrails Other architectural finishes Installation of station and other signs Installation of a fountain Planting and irrigation system Installation of false ceilings at the ticketing…
Μάθε Περισσότερα
Επίσκεψη του Γενικού Γραμματέα Υποδομών στο Μετρό Θεσσαλονίκης

Mr. George Karayiannis, Secretary General of Infrastructures, visits Thessaloniki Metro

  Statements made by Mr. George Karayiannis, Secretary General of Infrastructures, on the progress of Thessaloniki Metro works   Mr. George Karayiannis, Secretary General of Infrastructures, visited today the city of Thessaloniki, in order to be informed on the progress of the Metro works. His first stop was Pylea Depot,…
Μάθε Περισσότερα
Σύσκεψη μεταξύ των φορέων ΑΤΤΙΚΟ ΜΕΤΡΟ Α.Ε. και Ο.Σ.Ε.Θ.

Meeting held between representatives of ATTIKO METRO S.A. and Thessaloniki Transport Authority (OSETH)

  In the presence of Mr. George Karayiannis, Secretary General of Infrastructures, a meeting was held between representatives of ATTIKO METRO S.A. and Thessaloniki Transport Authority (OSETH). More specifically, Mr. Nikolaos Tachiaos, Chairman of ATTIKO METRO S.A., Mr. Nikolaos Kouretas, CEO of ATTIKO METRO S.A., Mr. Ioannis Kalogeroudis, Chairman of…
Μάθε Περισσότερα
Πρόοδος έργου ΤΡΑΜ - Ιανουάριος 2020

JANUARY 2020

  By order of the Traffic Police, ATTIKO METRO S.A. interrupted the tramway circulation for safety reasons further to the unfortunate event of a fire that burst onto a listed building located on Omiridou Skylitsi Street on 03.01.2020 adjacent to the tramway. Further to this incident, this privately owned building…
Μάθε Περισσότερα

December 2019

NOMARCHIA Station (station & crossover): Painting works have been completed at the track level of the crossover. The works for the construction of metal items in the surrounding area of the station are in progress. KALAMARIA Station: The works for the installation of outdoor staircases have been completed. Pontou shaft:…
Μάθε Περισσότερα

December 2019

NEW RAILWAY STATION: Works for the reinstatement of the indoor lift and works for the preparation of the tunnel filling concrete are in progress. DIMOKRATIAS Station (Station & Crossover): In the framework of the 30th Traffic Reinstatement Plan, works for the construction of the central island at Monastiriou Street have…
Μάθε Περισσότερα

DECEMBER 2019

DOUBLE TRACK NATM START TUNNEL Works have been completed. KOMNINOU SHAFT The following works have been completed: Masonry, plastering, door installation, industrial floor, painting, grid installation at street level, staircase balustrades, hatch Street level reinstatement AGHIA VARVARA STATION The following works are in progress: Installation of lifts in the station…
Μάθε Περισσότερα