Kalamaria Project progress

January 2018

Nomarchia Station: The implementation of phase C’ of traffic arrangements and the construction of retaining piles at the north access (at a part of Vas. Olgas street) have been completed. Plastering works are in progress. • KALAMARIA Station: In progress is the construction of the permanent lining and waterproofing of…
Μάθε Περισσότερα

April 2017

NOMARCHIA Station: The permanent lining at level -1 has been completed. Works for the construction of the slab at level -2 are in progress. • KALAMARIA Station: The construction of the permanent lining at level -3 has been completed. The construction of the slab at level -2 is in progress.…
Μάθε Περισσότερα

January 2017

• NOMARCHIA Station: The construction of the slab at level -2 has been completed, while in progress is the construction of the permanent lining from level -2 to level -1. • NOMARCHIA Crossover: In progress is the construction of the permanent lining from level -1 to the roof level. •…
Μάθε Περισσότερα

November 2016

NOMARCHIA Station: The construction of the permanent lining from the foundation slab up to level -2 is in progress. NOMARCHIA Crossover: The construction of the permanent lining from the foundation slab up to level -1 was completed. In progress is the construction of the slab of level -1 and the…
Μάθε Περισσότερα

October 2016

NOMARCHIA Station: The waterproofing of masonry walls from the foundation slab to level -1 has been completed, while in progress is the construction of the platform. NOMARCHIA Crossover: The waterproofing of masonry walls from the foundation slab to level -1 has been completed. In progress is the construction of scaffolding…
Μάθε Περισσότερα

September 2016

NOMARCHIA Station: The works for the construction of the foundation slab have been completed. The construction of the permanent lining from the foundation slab up to level -1 is in progress. Nomarchia Junction: The construction of the foundation slab is completed. The removal of the struts at the last level…
Μάθε Περισσότερα

August 2016

NOMARCHIA Station: The works for the construction of the foundation slab are in progress. KALAMARIA Station: The works for the temporary retaining of the metal struts up to the 4th level are in progress. ARETSOU Station: The installation of metal struts at the 2nd level has been completed. In progress…
Μάθε Περισσότερα

June 2016

NOMARCHIA Crossover: The works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert. KALAMARIA Station: The installation of metal struts at the 2nd level have been completed. In progress are the excavation works…
Μάθε Περισσότερα

May 2016

NOMARCHIA Station: The excavation of level -3 of the station, as well as the works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert. NOMARCHIA Crossover: The excavation works of level -3 have…
Μάθε Περισσότερα

March 2016

NOMARCHIA Station: The works for the installation of metal struts at level -2 are in progress. NOMARCHIA Crossover: The works for the installation of metal struts at level -1 were completed. The excavation works of level -2 and the works for the installation of metal struts at level -2 are…
Μάθε Περισσότερα