Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

Kalamaria Project progress

April 2015

NOMARCHIA Station and Crossover: Piling works for the temporary retaining and the foundation of the building crane have commenced. Works for the occupation of the worksite are in progress, while works for the diversion of PUO networks are at an advanced stage; KALAMARIA Station: Works for the occupation of the…
Μάθε Περισσότερα

March 2015

The works for the construction of a street parallel to Mitropoliti Kydonion Grigoriou Street within the area of the former Farmaki Military Camp, extending between G. Papandreou and V. Olgas Streets, as well as the works for the construction of a connecting road with Ifigenias Street have been completed. Moreover,…
Μάθε Περισσότερα

February 2015

NOMARCHIA Station & Crossover: The works for the diversion of the central sewage pipe have been completed. At an advanced stage are the works for the construction of a street parallel to Mitropoliti Kydonion Grigoriou Street within the area of the former Farmaki Military Camp, extending between G. Papandreou and…
Μάθε Περισσότερα

January 2015

NOMARHIA Station & Crossover: The works for the construction of pits for the diversion of the central sewage pipe, the works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp, as well as the works for the…
Μάθε Περισσότερα

December 2014

NOMARCHIA Station & Crossover: The works concerning the diversion of the sewage pipe through micro-TBM underground boring have been completed. The works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp, as well as the PUO network…
Μάθε Περισσότερα

November 2014

NOMARHIA Station & Crossover: The works concerning the diversion of the 1stbranch of the sewage pipe through TBM underground boring have been completed. The works for the diversion of traffic from Mitropoliti Kydonion Grigoriou street into a new street within the area of the former Farmaki camp have commenced; KALAMARIA…
Μάθε Περισσότερα

October 2014

NOMARCHIA Station: The works for the construction of shafts for the diversion of the sewage network are in progress; KALAMARIA Station: The works for the diversion of PUO networks are in progress; NEA KRINI Station: The works for the diversion of PUO networks have commenced, while the works for the…
Μάθε Περισσότερα

September 2014

NOMARCHIA Station: The works for the construction of shafts for the diversion of the sewage network have commenced; KALAMARIA Station: The works for the diversion of PUO networks have commenced; MIKRA Station: The excavation and retaining works at the TBMs access shaft are in progress; The preparation of designs is…
Μάθε Περισσότερα

July 2014

The works for the construction of piles for peripheral retaining, as well as excavation works at NEA KRINI Station have commenced; The preparation, review and approval of the designs for the relocation and diversion of PUO networks, the traffic arrangements-diversions and the final designs of the stations are at an…
Μάθε Περισσότερα
WCAG